PROJECT STATUS REPORT
Recommendation:
It is recommended that Council receive and
file this report.
Summary:
This report gives the status of capital
improvement projects that are either under design or
construction. Capital improvement projects not indicated in
this report can be found in the department’s Monthly
Activity Report.
Project Status:
project no. cip 00-139 hermosa avenue
street improvements, 16th street to 26th street
description
|
status
|
|
|
preliminary engineering
|
completed 03-20-00
|
design & engineering
(ps&e)
|
in progress
|
to pw commission for review
|
04-01
|
to council for approval to
advertise
|
04-01
|
bid opening
|
04-01
|
to council for award
|
05-01
|
begin construction
|
06-01
|
end construction
|
08-01
|
project no. cip 99-144 strand bikeway &
pedestrian walkway reconstruction between 24th and 35th
street
description
|
status
|
|
|
preliminary engineering
|
completed 05-25-99
|
design & engineering
(ps&e)
|
completed 10-05-00
|
to pw commission for review
|
n/a
|
to council for approval to
advertise
|
completed 05-02-00
|
bid opening
|
completed 10-12-00
|
to council for award
|
completed 11-14-00
|
begin construction
|
completed 01-16-01
|
end construction
|
04-01
|
project no. cip 95-150 hermosa avenue
street improvements, between pier and 16th
description
|
status
|
|
|
preliminary engineering
|
completed 05-17-99
|
design & engineering
(ps&e)
|
completed 03-27-00
|
to pw commission for review
|
n/a
|
to council for approval to
advertise
|
completed 04-25-00
|
bid opening
|
completed 06-15-00
|
to council for award
|
completed 07-11-00
|
begin construction
|
completed 09-05-00
|
end construction
|
completed 03-13-01
|
Indicates Construction Completed
project no. cip 00-171 ardmore street
improvements
description
|
status
|
|
|
preliminary engineering
|
completed 12-21-00
|
design & engineering
(ps&e)
|
completed 02-01
|
to pw commission for review
|
03-14-01
|
to council for information
purposes
|
03-13-01
|
bid opening
|
03-19-01
|
to council for award
|
03-27-01
|
begin construction
|
05-01
|
end construction
|
08-01
|
project no. cip 00-172 2st street - valley
to power street improvements
description
|
status
|
|
|
preliminary engineering
|
completed 12-21-00
|
design & engineering
(ps&e)
|
03-01
|
to pw commission for review
|
04-01
|
to council for approval to
advertise
|
05-01
|
bid opening
|
06-01
|
to council for award
|
06-01
|
begin construction
|
07-01
|
end construction
|
09-01
|
project no. cip 00-192 loma area street
improvements
description
|
status
|
|
|
preliminary engineering
|
completed 03-08-00
|
design & engineering
(ps&e)
|
05-01
|
to pw commission for review
|
07-01
|
to council for approval to
advertise
|
08-01
|
bid opening
|
01-02
|
to council for award
|
02-02
|
begin construction
|
03-02
|
end construction
|
08-02
|
project no. cip 99-305 installation of
continuos deflection screen (cds) storm water clarifier
units
description
|
status
|
|
|
design & engineering
(ps&e)
|
completed 11-20-00
|
obtain permit from the county
|
in progress
|
to pw commission for review
|
n/a
|
to council for approval to
advertise
|
04-01
|
bid opening
|
05-01
|
to council for award
|
06-01
|
begin construction
|
06-01
|
end construction
|
09-01
|
project no. cip 99-306 installation of
catch basin inlet filters
description
|
status
|
|
|
preliminary engineering/grant
application
|
completed 11-24-98
|
design & engineering
(ps&e)
|
completed 06-06-00
|
to pw commission for review
|
n/a
|
to council for approval to
advertise
|
06-13-00
|
bid opening
|
06-29-00
|
to council for award
(design/build)
|
07-11-00
|
begin construction
|
in progress
|
end construction
|
04-01
|
project no. cip 99-409 manhole
repair/sewer reconstruction – 24th street, beach
dr. and the strand
description
|
status
|
|
|
preliminary engineering
|
completed 08-30-00
|
design & engineering
(ps&e)
|
completed 09-05-00
|
to pw commission for review
|
n/a
|
to council for approval to
advertise
|
09-12-00
|
bid opening
|
10-18-00
|
to council for award
|
10-24-00
|
begin construction
|
11-27-00
|
end construction
|
completed 12-18-00
|
project no. cip 00-410 loma area
sewer improvements
description
|
status
|
|
|
preliminary engineering
|
completed 03-08-00
|
design & engineering
(ps&e)
|
04-01
|
to pw commission for review
|
04-01
|
to council for approval to
advertise
|
05-01
|
bid opening
|
06-01
|
to council for award
|
06-01
|
begin construction
|
07-01
|
end construction
|
02-02
|
project no. cip 95-507 valley park
improvements
description
|
status
|
|
|
preliminary engineering
|
completed 06-24-99
|
design & engineering
(ps&e)
|
in progress
|
to pw commission for review
|
04-01
|
to council for approval to
advertise
|
04-01
|
bid opening
|
05-01
|
to council for award
|
05-01
|
begin construction
|
06-01
|
end construction
|
12-01
|
project no. cip 99-529 clark field
improvements - ballfield backstop
description
|
status
|
|
|
preliminary engineering
|
completed 10-18-99
|
design & engineering
(ps&e)
|
completed 06-12-00
|
to pw commission for review
|
n/a
|
to council for approval to
advertise
|
10-10-00
|
bid opening
|
11-09-00
|
to council for award
|
11-28-00
|
begin construction
|
01-08-01
|
end construction
|
03-01
|
project no. cip 99-530 various park
improvements - south park roller hockey
description
|
status
|
|
|
preliminary engineering
|
completed 05-08-00
|
design & engineering
(ps&e)
|
completed 10-23-00
|
to pw commission for review
|
n/a
|
to council for approval to
advertise
|
11-28-00
|
bid opening
|
12-07-00
|
to council for approval to
re-bid
|
02-27-01
|
bid opening
|
04-01
|
to council for award
|
05-01
|
begin construction
|
06-01
|
end construction
|
09-01
|
project no. cip 98-621 pier renovation, phase
ii
description
|
status
|
|
|
preliminary engineering
|
completed 03-25-97
|
design & engineering
(ps&e)
|
completed 11-02-99
|
to pw commission for review
|
n/a
|
to council for approval to
advertise
|
11-09-99
|
bid opening
|
12-16-99
|
to council for award
|
01-25-00
|
begin construction
|
03-06-00
|
end construction
|
completed
|
acceptance/notice of completion
|
02-13-01
|
project no. cip 95-622 city hall remodel
– ada upgrades
description
|
status
|
|
|
preliminary engineering
|
completed
|
design & engineering
(ps&e)
|
in progress
|
to pw commission for review
|
n/a
|
cm agreement to council for
approval
|
completed 11-28-00
|
constructibility review
|
in progress
|
relocation programming
|
in progress
|
to council for approval of plans &
specs, advertise
|
04-01
|
bid opening
|
05-01
|
to council for award
|
06-01
|
begin construction
|
07-01
|
end construction
|
06-02
|
project no. cip 99-627 community center
improvements - fencing
description
|
status
|
|
|
preliminary engineering
|
completed 05-08-00
|
design & engineering
(ps&e)
|
completed 10-23-00
|
to pw commission for review
|
n/a
|
to council for approval to
advertise
|
11-14-00
|
bid opening
|
12-07-00
|
to council for award
|
01-09-01
|
begin construction
|
03-12-01
|
end construction
|
04-01
|
project no. cip 00-630 pier renovation,
phase iii
description
|
status
|
|
|
preliminary engineering
|
completed 03-08-00
|
design & engineering
(ps&e)
|
04-01
|
to pw commission for review
|
05-01
|
to council for approval to
advertise
|
05-01
|
bid opening
|
08-01
|
to council for award
|
09-01
|
begin construction
|
10-01
|
end construction
|
11-02
|