City of Hermosa Beach --- 06-27-00

CIP PROJECT 99-409 SEWER RECONSTRUCTION AND
REHABILITATION ON PACIFIC COAST HIGHWAY BETWEEN
GOULD AVENUE AND 24TH STREET - ACCEPTANCE

 

Recommendation :

It is recommended that the City Council:

  1. Accept the work by U-Liner West for CIP Project No. 99-409 PCH Sewer Reconstruction,
  2. Authorize the Mayor to sign the Notice of Completion,
  3. Authorize Staff to release payment to U-Liner West (5% retained for 35 days following filing of Notice of Completion), and
  4. Authorize City Clerk to release U-Liner West from the Faithful Performance Bond and the Labor and Materials Bond.

 

Background :

On March 28, 2000, City Council approved entering into an agreement with U-Liner West to construct the Pacific Coast Highway Sewer Rehabilitation between Gould Avenue and 24th Street. The proposed work included reconstruction of approximately 40 feet of 8" VCP and installing 400 feet of in-place cured lining and appurtenant work.

The contractor has completed the work to the satisfaction of the Director of Public Works/City Engineer.

 

Fiscal Impact :

This project was completed within budget and ahead of schedule, therefore, no additional appropriation is required.

The work was funded out of account no. 160-8409-4201, $28,250. The balance of this account is $106,750.