City of Hermosa Beach --- 01-09-01

CIP 99-409 MANHOLE REPAIR/SEWER RECONSTRUCTION AT
24TH STREET, BEACH DRIVE AND THE STRAND - ACCEPTANCE

 

Recommendation :

It is recommended that the City Council:

  1. Accept the work by Atlas Underground Co. for Project No. CIP 99-409 Manhole Repair/Sewer Reconstruction at 24th Street, Beach Drive and The Strand.
  2. Authorize the Mayor to sign the Notice of Completion.
  3. Authorize Staff to release payment to Atlas Underground Co. (5% retained for 35 days following filing of Notice of Completion).

 

Background :

On October 24, 2000, City Council awarded the contract for Manhole Repair/Sewer Reconstruction at the intersections of 24th Street and The Strand and 24th Street and Beach Drive. The proposed work for the project included, in general, the complete construction of a new sewer main, manholes, service connections, trench restoration and street pavement.

The contractor has completed the work to the satisfaction of the Director of Public Works/City Engineer.

 

Analysis:

  1. The project was constructed according to the plans, specifications and a change order. Staff, therefore, recommends acceptance of the work as complete.
  2. The project was completed within the appropriated budget of $57,318.

Fiscal Impact :

  1. Original Contract Amount     $ 49,842

  2. Change Order #1                    $ 7,400

  3. Total Construction Cost       $ 57,242