City of Hermosa Beach --- 05-25-99


CIP PROJECT NO. 98-142

MONTEREY BLVD STREET IMPROVEMENTS

PIER AVENUE TO 19TH STREET - ACCEPTANCE



Recommendation:


It is recommended that the City Council accept the work by Sully- Miller Contracting Company, of Anaheim, on CIP Project No. 98-142, Street Improvements, and authorize final payment to the contractor (10% retained for 35 days following filing of Certificate of Completion).


Background:


On January 12, 1999, City Council approved entering into an agreement with Sully-Miller Contracting Company, of Anaheim, to perform a complete street resurfacing with minor public right-of-way improvements and the lining of three selected lengths of existing sewer pipe within Monterey Boulevard between, Pier Avenue to 19th Street. The work included:


  • Replace various concrete wheelchair ramps and driveway approaches
  • Replace cross-gutters and minor sidewalk replacement
  • Sewer lining
  • Crack Sealing
  • Street resurfacing and striping


The contractor has completed the work to the satisfaction of the Director of Public Works/City Engineer.


Analysis:


Acceptance of the work and final payment is in order. The original contract amount was $163,775. Sully-Miller Contracting Company completed the work for $160,770.58, saving the City $3,004.42.


Fiscal Impact:


The project was completed under budget, therefore, $3,004.42 can be returned to fund 301 CIP.