City of Hermosa Beach --- 07-11-00
PROJECT NO. CIP 99-529 CLARK FIELD
IMPROVEMENTS, BUILDING DEMOLITION
Recommendation: It is recommended that the City Council:
Background: On January 25, 2000, Council awarded a construction contract to Viking Equipment Corp. (Contractor) for the demolition of the enclosed storage area (building) located at Clark Field. The award was based on the Contractor’s low bid price of $8,300. During the demolition work, it was discovered that what initially appeared to be a retaining wall behind the building wall was, in fact, a row of cement blocks without any structural value. The building’s wall had been acting as a retaining wall, holding back the existing slope located behind the building. The Contractor was ordered to stop work until further engineering evaluation of the wall was performed. (click on the thumbnail below for a larger photo.) Staff engaged the services of an engineering firm, Jonathan E. Mahn, P.E., to evaluate the building wall and to provide design and recommendations. The engineering report has been completed and provides the following findings and recommendations:
Based upon the engineering design provided by the consultant, Staff has obtained a proposal from the Contractor to construct the retaining wall structure for $33,239.00. The proposed work will be completed within 45 days from the date of the notice to proceed. Accordingly, the project can be completed ahead of the rainy season.
Analysis: Since this project cannot be completed without protecting the slope behind the wall, Staff recommends that the Contractor perform the necessary work under a Supplemental Agreement for the following reasons:
Therefore, Staff is recommending that City Council authorize Staff to execute a Supplemental Agreement with the Contractor in the amount of $33,239.00.
Alternatives:
Fiscal Impact: Sufficient funds were available in the 1999-00 project budget; however, there was no opportunity to spend all funds appropriated for this project. Therefore, Staff is requesting that the funds ($119,000 in account number 125-8529-4201) be re-appropriated in the FY 2000-01 budget. CONTRACT CHANGE ORDER
Project Title: Clark Field Building Demolition The changes or interpretations described and noted herein are hereby authorized. The signed original of this order is on file at the office of the Director of Public Works/City Engineer. Show as separate numbered paragraphs: (1) Reason for change; (2) Description of change; (3) Change in contract cost; (4) Extension of contract, if warranted; (5) New contract total including all change orders; SUPPLEMENTAL AGREEMENT 1. To construct a retaining wall to replace existing building wall. 2. Construct retaining wall in accordance with design criteria prepared by Bryce D. Richmond, sheets 1-4, dated 6/6/00 and Jonathan Mahn, dated 6/2/00. Sawcut and remove existing concrete slab at area of new wall only. Excludes: waterproofing membrane at back side of retaining wall, survey and engineering. 3. $33,239.00 4. 45 days 5. $45,299.00 |
|