City of Hermosa Beach --- 07-13-99

 

CIP PROJECT NO. 97-525

COMMUNITY CENTER SKATE TRACK

ACCEPTANCE

 

Recommendation :

It is recommended that the City Council accept the work by Asan Construction Company, of Calabasas, for CIP Project No. 97-525, Community Center Skate Track and authorize final payment to the contractor (10% retained for 35 days following filing of Certificate of Completion).

Background :

On January 26, 1999, City Council approved entering into an agreement with Asan Construction Company, of Calabasas, to construct the Community Center Skate Track. The work included:

  • Demolition of the existing tennis courts
  • Site grading
  • Installation of concrete flatwork and concrete skate track elements
  • Installation of metalwork
  • Installation of chainlink fencing
  • Installation of asphalt concrete for new parking area

The contractor has completed the work to the satisfaction of the Director of Public Works/City Engineer.

Analysis :

Acceptance of the work and final payment is in order. The original contract amount was $115,280. Asan Construction Company completed the work for $113,533, saving the City $1,747.

Fiscal Impact :

The project was completed $1,747 under budget.