City of Hermosa Beach --- 12-12-00

PROJECT STATUS REPORT

 

Recommendation:

It is recommended that Council receive and file this report.

 

Summary:

This report gives the status of capital improvement projects that are either under design or construction. Capital improvement projects not indicated in this report can be found in the department’s Monthly Activity Report.

 

Project Status:

project no. cip 00-139 hermosa avenue street improvements, 16th street to 26th street

description

completion date

preliminary engineering

completed

design & engineering (ps&e)

in progress

to pw commission for review

n/a

to council for approval to advertise

02-13-01

bid opening

03-08-01

to council for award

03-27-01

begin construction

04-16-01

end construction

06-18-01

 

project no. cip 99-144 strand bikeway & pedestrian walkway reconstruction between 24th and 35th streets

description

completion date

preliminary engineering

completed

design & engineering (ps&e)

completed

to pw commission for review

n/a

to council for approval to advertise

completed

bid opening

completed

to council for award

completed

begin construction

01-01

end construction

04-01

 

project no. cip 95-150 hermosa avenue street improvements, between pier and 16th street

description

completion date

preliminary engineering

completed

design & engineering (ps&e)

completed

to pw commission for review

n/a

to council for approval to advertise

completed

bid opening

completed

to council for award

completed

begin construction

in progress

end construction

12-20-00

 

project no. cip 00-171 ardmore street improvements

description

completion date

preliminary engineering

completed

design & engineering (ps&e)

02-01

to pw commission for review

03-01

to council for approval to advertise

03-01

bid opening

03-01

to council for award

04-01

begin construction

05-01

end construction

07-01

 

project no. cip 00-172 21st street - valley to power street improvements

description

completion date

preliminary engineering

11-00

design & engineering (ps&e)

02-01

to pw commission for review

02-01

to council for approval to advertise

02-13-01

bid opening

03-08-01

to council for award

03-27-01

begin construction

05-01

end construction

07-01

   

 

project no. cip 00-192 loma area street improvements

description

completion date

preliminary engineering

completed

design & engineering (ps&e)

03-01

to pw commission for review

07-01

to council for approval to advertise

08-01

bid opening

09-01

to council for award

10-01

begin construction

01-02

end construction

03-02

 

project no. cip 99-305 installation of continuos deflection screen (cds) storm water clarifier units

description

completion date

preliminary engineering

completed

obtain permit from the county

in progress

design & engineering (ps&e)

in progress

to pw commission for review

n/a

to council for approval to advertise

03-13-01

bid opening

04-03-01

to council for award

04-10-01

begin construction

05-07-01

end construction

07-31-01

 

project no. cip 99-306 installation of catch basin inlet filters

description

completion date

preliminary engineering

completed

design & engineering (ps&e)

completed

to pw commission for review

n/a

to council for approval to advertise

completed

bid opening

completed

to council for award

completed

begin construction

in progress

end construction

01-23-01

 

project no. cip 99-409 manhole repair/sewer reconstruction – 24th street, beach dr. and the strand

description

completion date

preliminary engineering

completed

design & engineering (ps&e)

completed

to pw commission for review

n/a

to council for approval to advertise

completed

bid opening

completed

to council for award

completed

begin construction

11-20-00

end construction

12-18-00

 

project no. cip 00-410 loma area sewer improvements

description

completion date

preliminary engineering

completed

design & engineering (ps&e)

02-01

to pw commission for review

12-00

to council for approval to advertise

03-01

bid opening

04-01

to council for award

05-01

begin construction

06-01

end construction

01-02

 

project no. cip 95-507 valley park improvements

description

completion date

preliminary engineering

completed

design & engineering (ps&e)

in progress

to pw commission for review

01-01

to council for approval to advertise

01-23-01

bid opening

02-22-01

to council for award

03-13-01

begin construction

04-02-01

end construction

09-03-01

 

project no. cip 99-529 clark field improvements - ballfield backstop

description

completion date

preliminary engineering

completed

design & engineering (ps&e)

completed

to pw commission for review

n/a

to council for approval to advertise

10-10-00

bid opening

11-09-00

to council for award

11-28-00

begin construction

01-08-01

end construction

02-16-01

 

project no. cip 99-530 various park improvements - south park roller hockey

description

completion date

preliminary engineering

completed

design & engineering (ps&e)

in progress

to pw commission for review

n/a

to council for approval to advertise

11-14-00

bid opening

12-12-00

to council for award

01-09-01

begin construction

02-05-01

end construction

04-30-01

 

project no. cip 98-621 pier renovation, phase ii

description

completion date

preliminary engineering

completed

design & engineering (ps&e)

completed

to pw commission for review

n/a

to council for approval to advertise

completed

bid opening

completed

to council for award

completed

begin construction

completed

end construction

12-15-00 remaining punchlist items

 

project no. cip 95-622 city hall remodel – ada upgrades

description

completion date

preliminary engineering

completed

design & engineering (ps&e)

in progress

to pw commission for review

n/a

cm agreement to council for approval

11-28-00

constructibility review

in progress

relocation programming

in progress

to council for approval of plans & specs, advertise

01-23-01

bid opening

02-22-01

to council for award

03-13-01

begin construction

04-02-01

 

project no. cip 99-627 community center improvements - fencing

description

completion date

preliminary engineering

completed

design & engineering (ps&e)

completed

to pw commission for review

n/a

to council for approval to advertise

11-14-00

bid opening

12-07-00

to council for award

01-09-01

begin construction

02-05-01

end construction

03-26-01

 

project no. cip 00-630 pier renovation, phase iii

description

completion date

preliminary engineering

completed

design & engineering (ps&e)

04-01

to pw commission for review

 

to council for approval to advertise

05-01

bid opening

08-01

to council for award

09-01

begin construction

10-01

end construction

11-02