PROJECT STATUS REPORT
Recommendation:
It is recommended that Council receive and file this
report.
Summary:
This report gives the status of capital
improvement projects that are either under design or
construction. Capital improvement projects not indicated in
this report can be found in the department’s Monthly
Activity Report.
Project Status:
project no. cip 00-139 hermosa avenue street improvements,
16th street to 26th street
|
description
|
completion date
|
|
preliminary engineering
|
completed
|
|
design & engineering (ps&e)
|
in progress
|
|
to pw commission for review
|
n/a
|
|
to council for approval to advertise
|
02-13-01
|
|
bid opening
|
03-08-01
|
|
to council for award
|
03-27-01
|
|
begin construction
|
04-16-01
|
|
end construction
|
06-18-01
|
project no. cip 99-144 strand bikeway &
pedestrian walkway reconstruction between 24th and 35th
streets
|
description
|
completion date
|
|
preliminary engineering
|
completed
|
|
design & engineering (ps&e)
|
completed
|
|
to pw commission for review
|
n/a
|
|
to council for approval to advertise
|
completed
|
|
bid opening
|
completed
|
|
to council for award
|
completed
|
|
begin construction
|
01-01
|
|
end construction
|
04-01
|
project no. cip 95-150 hermosa avenue street
improvements, between pier and 16th street
|
description
|
completion date
|
|
preliminary engineering
|
completed
|
|
design & engineering (ps&e)
|
completed
|
|
to pw commission for review
|
n/a
|
|
to council for approval to advertise
|
completed
|
|
bid opening
|
completed
|
|
to council for award
|
completed
|
|
begin construction
|
in progress
|
|
end construction
|
12-20-00
|
project no. cip 00-171 ardmore street
improvements
|
description
|
completion date
|
|
preliminary engineering
|
completed
|
|
design & engineering (ps&e)
|
02-01
|
|
to pw commission for review
|
03-01
|
|
to council for approval to advertise
|
03-01
|
|
bid opening
|
03-01
|
|
to council for award
|
04-01
|
|
begin construction
|
05-01
|
|
end construction
|
07-01
|
project no. cip 00-172 21st street - valley
to power street improvements
|
description
|
completion date
|
|
preliminary engineering
|
11-00
|
|
design & engineering (ps&e)
|
02-01
|
|
to pw commission for review
|
02-01
|
|
to council for approval to advertise
|
02-13-01
|
|
bid opening
|
03-08-01
|
|
to council for award
|
03-27-01
|
|
begin construction
|
05-01
|
|
end construction
|
07-01
|
| |
|
project no. cip 00-192 loma area street
improvements
|
description
|
completion date
|
|
preliminary engineering
|
completed
|
|
design & engineering (ps&e)
|
03-01
|
|
to pw commission for review
|
07-01
|
|
to council for approval to advertise
|
08-01
|
|
bid opening
|
09-01
|
|
to council for award
|
10-01
|
|
begin construction
|
01-02
|
|
end construction
|
03-02
|
project no. cip 99-305 installation of
continuos deflection screen (cds) storm water clarifier
units
|
description
|
completion date
|
|
preliminary engineering
|
completed
|
|
obtain permit from the county
|
in progress
|
|
design & engineering (ps&e)
|
in progress
|
|
to pw commission for review
|
n/a
|
|
to council for approval to advertise
|
03-13-01
|
|
bid opening
|
04-03-01
|
|
to council for award
|
04-10-01
|
|
begin construction
|
05-07-01
|
|
end construction
|
07-31-01
|
project no. cip 99-306 installation of catch
basin inlet filters
|
description
|
completion date
|
|
preliminary engineering
|
completed
|
|
design & engineering (ps&e)
|
completed
|
|
to pw commission for review
|
n/a
|
|
to council for approval to advertise
|
completed
|
|
bid opening
|
completed
|
|
to council for award
|
completed
|
|
begin construction
|
in progress
|
|
end construction
|
01-23-01
|
project no. cip 99-409 manhole repair/sewer
reconstruction – 24th street, beach dr. and the
strand
|
description
|
completion date
|
|
preliminary engineering
|
completed
|
|
design & engineering (ps&e)
|
completed
|
|
to pw commission for review
|
n/a
|
|
to council for approval to advertise
|
completed
|
|
bid opening
|
completed
|
|
to council for award
|
completed
|
|
begin construction
|
11-20-00
|
|
end construction
|
12-18-00
|
project no. cip 00-410 loma area
sewer improvements
|
description
|
completion date
|
|
preliminary engineering
|
completed
|
|
design & engineering (ps&e)
|
02-01
|
|
to pw commission for review
|
12-00
|
|
to council for approval to advertise
|
03-01
|
|
bid opening
|
04-01
|
|
to council for award
|
05-01
|
|
begin construction
|
06-01
|
|
end construction
|
01-02
|
project no. cip 95-507 valley park
improvements
|
description
|
completion date
|
|
preliminary engineering
|
completed
|
|
design & engineering (ps&e)
|
in progress
|
|
to pw commission for review
|
01-01
|
|
to council for approval to advertise
|
01-23-01
|
|
bid opening
|
02-22-01
|
|
to council for award
|
03-13-01
|
|
begin construction
|
04-02-01
|
|
end construction
|
09-03-01
|
project no. cip 99-529 clark field
improvements - ballfield backstop
|
description
|
completion date
|
|
preliminary engineering
|
completed
|
|
design & engineering (ps&e)
|
completed
|
|
to pw commission for review
|
n/a
|
|
to council for approval to advertise
|
10-10-00
|
|
bid opening
|
11-09-00
|
|
to council for award
|
11-28-00
|
|
begin construction
|
01-08-01
|
|
end construction
|
02-16-01
|
project no. cip 99-530 various park
improvements - south park roller hockey
|
description
|
completion date
|
|
preliminary engineering
|
completed
|
|
design & engineering (ps&e)
|
in progress
|
|
to pw commission for review
|
n/a
|
|
to council for approval to advertise
|
11-14-00
|
|
bid opening
|
12-12-00
|
|
to council for award
|
01-09-01
|
|
begin construction
|
02-05-01
|
|
end construction
|
04-30-01
|
project no. cip 98-621 pier renovation, phase
ii
|
description
|
completion date
|
|
preliminary engineering
|
completed
|
|
design & engineering (ps&e)
|
completed
|
|
to pw commission for review
|
n/a
|
|
to council for approval to advertise
|
completed
|
|
bid opening
|
completed
|
|
to council for award
|
completed
|
|
begin construction
|
completed
|
|
end construction
|
12-15-00 remaining punchlist items
|
project no. cip 95-622 city hall remodel
– ada upgrades
|
description
|
completion date
|
|
preliminary engineering
|
completed
|
|
design & engineering (ps&e)
|
in progress
|
|
to pw commission for review
|
n/a
|
|
cm agreement to council for approval
|
11-28-00
|
|
constructibility review
|
in progress
|
|
relocation programming
|
in progress
|
|
to council for approval of plans & specs,
advertise
|
01-23-01
|
|
bid opening
|
02-22-01
|
|
to council for award
|
03-13-01
|
|
begin construction
|
04-02-01
|
project no. cip 99-627 community center
improvements - fencing
|
description
|
completion date
|
|
preliminary engineering
|
completed
|
|
design & engineering (ps&e)
|
completed
|
|
to pw commission for review
|
n/a
|
|
to council for approval to advertise
|
11-14-00
|
|
bid opening
|
12-07-00
|
|
to council for award
|
01-09-01
|
|
begin construction
|
02-05-01
|
|
end construction
|
03-26-01
|
project no. cip 00-630 pier renovation, phase
iii
|
description
|
completion date
|
|
preliminary engineering
|
completed
|
|
design & engineering (ps&e)
|
04-01
|
|
to pw commission for review
|
|
|
to council for approval to advertise
|
05-01
|
|
bid opening
|
08-01
|
|
to council for award
|
09-01
|
|
begin construction
|
10-01
|
|
end construction
|
11-02
|