PROJECT STATUS REPORT
Recommendation:
It is recommended that Council receive and file this
report.
Summary:
This report gives the status of capital
improvement projects that are either under design or
construction. Capital improvement projects not indicated in
this report can be found in the department’s Monthly
Activity Report.
Project Status:
project no. cip 00-139 hermosa avenue street improvements,
16th street to 26th street
description
|
completion date
|
preliminary engineering
|
completed
|
design & engineering (ps&e)
|
in progress
|
to pw commission for review
|
n/a
|
to council for approval to advertise
|
02-13-01
|
bid opening
|
03-08-01
|
to council for award
|
03-27-01
|
begin construction
|
04-16-01
|
end construction
|
06-18-01
|
project no. cip 99-144 strand bikeway &
pedestrian walkway reconstruction between 24th and 35th
streets
description
|
completion date
|
preliminary engineering
|
completed
|
design & engineering (ps&e)
|
completed
|
to pw commission for review
|
n/a
|
to council for approval to advertise
|
completed
|
bid opening
|
completed
|
to council for award
|
completed
|
begin construction
|
01-01
|
end construction
|
04-01
|
project no. cip 95-150 hermosa avenue street
improvements, between pier and 16th street
description
|
completion date
|
preliminary engineering
|
completed
|
design & engineering (ps&e)
|
completed
|
to pw commission for review
|
n/a
|
to council for approval to advertise
|
completed
|
bid opening
|
completed
|
to council for award
|
completed
|
begin construction
|
in progress
|
end construction
|
12-20-00
|
project no. cip 00-171 ardmore street
improvements
description
|
completion date
|
preliminary engineering
|
completed
|
design & engineering (ps&e)
|
02-01
|
to pw commission for review
|
03-01
|
to council for approval to advertise
|
03-01
|
bid opening
|
03-01
|
to council for award
|
04-01
|
begin construction
|
05-01
|
end construction
|
07-01
|
project no. cip 00-172 21st street - valley
to power street improvements
description
|
completion date
|
preliminary engineering
|
11-00
|
design & engineering (ps&e)
|
02-01
|
to pw commission for review
|
02-01
|
to council for approval to advertise
|
02-13-01
|
bid opening
|
03-08-01
|
to council for award
|
03-27-01
|
begin construction
|
05-01
|
end construction
|
07-01
|
|
|
project no. cip 00-192 loma area street
improvements
description
|
completion date
|
preliminary engineering
|
completed
|
design & engineering (ps&e)
|
03-01
|
to pw commission for review
|
07-01
|
to council for approval to advertise
|
08-01
|
bid opening
|
09-01
|
to council for award
|
10-01
|
begin construction
|
01-02
|
end construction
|
03-02
|
project no. cip 99-305 installation of
continuos deflection screen (cds) storm water clarifier
units
description
|
completion date
|
preliminary engineering
|
completed
|
obtain permit from the county
|
in progress
|
design & engineering (ps&e)
|
in progress
|
to pw commission for review
|
n/a
|
to council for approval to advertise
|
03-13-01
|
bid opening
|
04-03-01
|
to council for award
|
04-10-01
|
begin construction
|
05-07-01
|
end construction
|
07-31-01
|
project no. cip 99-306 installation of catch
basin inlet filters
description
|
completion date
|
preliminary engineering
|
completed
|
design & engineering (ps&e)
|
completed
|
to pw commission for review
|
n/a
|
to council for approval to advertise
|
completed
|
bid opening
|
completed
|
to council for award
|
completed
|
begin construction
|
in progress
|
end construction
|
01-23-01
|
project no. cip 99-409 manhole repair/sewer
reconstruction – 24th street, beach dr. and the
strand
description
|
completion date
|
preliminary engineering
|
completed
|
design & engineering (ps&e)
|
completed
|
to pw commission for review
|
n/a
|
to council for approval to advertise
|
completed
|
bid opening
|
completed
|
to council for award
|
completed
|
begin construction
|
11-20-00
|
end construction
|
12-18-00
|
project no. cip 00-410 loma area
sewer improvements
description
|
completion date
|
preliminary engineering
|
completed
|
design & engineering (ps&e)
|
02-01
|
to pw commission for review
|
12-00
|
to council for approval to advertise
|
03-01
|
bid opening
|
04-01
|
to council for award
|
05-01
|
begin construction
|
06-01
|
end construction
|
01-02
|
project no. cip 95-507 valley park
improvements
description
|
completion date
|
preliminary engineering
|
completed
|
design & engineering (ps&e)
|
in progress
|
to pw commission for review
|
01-01
|
to council for approval to advertise
|
01-23-01
|
bid opening
|
02-22-01
|
to council for award
|
03-13-01
|
begin construction
|
04-02-01
|
end construction
|
09-03-01
|
project no. cip 99-529 clark field
improvements - ballfield backstop
description
|
completion date
|
preliminary engineering
|
completed
|
design & engineering (ps&e)
|
completed
|
to pw commission for review
|
n/a
|
to council for approval to advertise
|
10-10-00
|
bid opening
|
11-09-00
|
to council for award
|
11-28-00
|
begin construction
|
01-08-01
|
end construction
|
02-16-01
|
project no. cip 99-530 various park
improvements - south park roller hockey
description
|
completion date
|
preliminary engineering
|
completed
|
design & engineering (ps&e)
|
in progress
|
to pw commission for review
|
n/a
|
to council for approval to advertise
|
11-14-00
|
bid opening
|
12-12-00
|
to council for award
|
01-09-01
|
begin construction
|
02-05-01
|
end construction
|
04-30-01
|
project no. cip 98-621 pier renovation, phase
ii
description
|
completion date
|
preliminary engineering
|
completed
|
design & engineering (ps&e)
|
completed
|
to pw commission for review
|
n/a
|
to council for approval to advertise
|
completed
|
bid opening
|
completed
|
to council for award
|
completed
|
begin construction
|
completed
|
end construction
|
12-15-00 remaining punchlist items
|
project no. cip 95-622 city hall remodel
– ada upgrades
description
|
completion date
|
preliminary engineering
|
completed
|
design & engineering (ps&e)
|
in progress
|
to pw commission for review
|
n/a
|
cm agreement to council for approval
|
11-28-00
|
constructibility review
|
in progress
|
relocation programming
|
in progress
|
to council for approval of plans & specs,
advertise
|
01-23-01
|
bid opening
|
02-22-01
|
to council for award
|
03-13-01
|
begin construction
|
04-02-01
|
project no. cip 99-627 community center
improvements - fencing
description
|
completion date
|
preliminary engineering
|
completed
|
design & engineering (ps&e)
|
completed
|
to pw commission for review
|
n/a
|
to council for approval to advertise
|
11-14-00
|
bid opening
|
12-07-00
|
to council for award
|
01-09-01
|
begin construction
|
02-05-01
|
end construction
|
03-26-01
|
project no. cip 00-630 pier renovation, phase
iii
description
|
completion date
|
preliminary engineering
|
completed
|
design & engineering (ps&e)
|
04-01
|
to pw commission for review
|
|
to council for approval to advertise
|
05-01
|
bid opening
|
08-01
|
to council for award
|
09-01
|
begin construction
|
10-01
|
end construction
|
11-02
|