City of Hermosa Beach --- 11-09-9

CIP PROJECT 98-621 PHASE II MUNICIPAL PIER ARCHITECTURAL UPGRADES – APPROVAL OF PLANS, SPECIFICATIONS & ESTIMATES AND ADVERTISE FOR BIDS

 

Recommendation :

It is recommended that the City Council:

  • Approve the plans, specifications, estimates, order the work and call for bids; and
  • Instruct the City Clerk to post Notice Inviting Sealed Bids for said project.

 

Background :

On April 27, 1999 Council approved an agreement with Concept Marine Associates, Inc. to prepare plans, specifications and estimates for Phase II Municipal Pier Architectural Upgrades. Concept Marine has completed the design and engineering work. The construction work will consist of deck surface repair work, work related to the installation of a new lighting system and safety railing along the pier and related work.

 

The plans, specifications and estimates are available in the office of the Director of Public Works/City Engineer for review.

 

Fiscal Impact :

The Engineer’s Estimate for construction is $1,314,867.00.