City of Hermosa Beach --- 07-27-99

 

PROJECT NO. CIP 99-143, MONTEREY BLVD.

IMPROVEMENTS - APPROVAL OF PLANS, SPECIFICATIONS & ESTIMATES AND ADVERTISE FOR BIDS

 

Recommendation :

It is recommended that the City Council:

1. Approve the plans, specifications, estimates, order the work and call for bids; and

2. Instruct the City Clerk to post a Notice Inviting Sealed Bids for said project.

 

Background :

The 1999-2000 Capital Improvement Project Budget included a project for the resurfacing of Monterey Boulevard, from 19 th Street to Hermosa Avenue. On February 9, 1999, Council approved an agreement between the City and DMR Team, Inc., for the preparation of plans, specifications and estimates (PS & E) for the project. The DMR team has completed the work.

The work to be performed consists of a complete street resurfacing with minor public right-of-way improvements. The public right-of-way improvements consist of replacing various concrete wheelchair ramps, driveway approaches, cross-gutters and a small amount of sidewalk replacement within the limits of work.

The PS & E’s are available in the office of the Director of Public Works/City Engineer for review.

 

Fiscal Impact:

The Engineer’s estimate for construction is $212,000.
 The current project budget is $275,555 from the Capital Improvement Fund 301.