PROJECT NO. CIP 00-630 PIER RENOVATION,
PHASE III
PROFESSIONAL SERVICES AGREEMENT
SECOND AMENDMENT
Recommendation
:
It is recommended that the City
Council:
- Approve the attached Second Amendment to the Professional
Services Agreement between the City of Hermosa Beach and
Purkiss
·
Rose – RSI for an increase in scope of services and
contract amount of $25,500;
- Authorize the City Clerk to attest and the Mayor to execute
said amendment, upon approval as to form by the City Attorney;
and
- Authorize the Director of Public Works/City Engineer to
make adjustments to the scope of work as necessary, not to
exceed $2,550.
Background
:
During the April 30, 2001, City Council
Workshop, decisions were made to revise the approved preliminary
design. The decisions are as follows:
- Delete proposed towers housing the electrical and
communications equipment is to be removed.
- Delete the planters/benches in the central wave
design.
- The background paving material depicted in light green on
the conceptual design shall be the same black architectural
concrete used in the lower downtown plaza area. In addition to
the current centerpiece wave design proposed, submit four (4)
additional conceptual plaza designs with different
centerpieces. One will be a compass rose. The second will be a
sunburst similar to the design on the observation deck. The
third and fourth designs will be up Purkiss
·
Rose to create. Also, when appropriate for the design,
incorporate the use of granite.
- For the restrooms on the south side of the plaza, the
individual restroom type with wood doors will remain in the
design. The sunburst in the pavement will be removed and the
black architectural concrete will be used instead. More light
and ventilation is to be incorporated into the design. The
position of the restroom building is to be rotated 180 degrees
so the sinks and showers face the ocean. The designer will
submit a conceptual design incorporating the previously stated
direction.
- The observation deck shall remain, but the stairs on the
east side of the ADA ramp connecting the Strand to the ramp are
to be removed. Submit three (3) additional conceptual designs
for the observation deck. One design will include the City
seal/logo. The second and third designs will be up Purkiss
·
Rose to create. Include bench locations at the periphery of
each design.
- Delete the parking pad on the north side of the plaza.
- Submit a conceptual design modifying the amphitheater
seating to include additional steps/seats leading down to the
sand. Include all required railing.
Through the design process, with numerous
meetings with Staff, Los Angeles County Lifeguards, the
Consultant, and the design subcommittee, and the Council, the
designer developed and submitted 50% construction drawings on
March 20, 2001. With direction to revise the design, additional
design fees are required to complete the increased scope of
services. See Attachment 1 for the April 30, 2001 City Council
Workshop minutes.
On February 8, 2000, City Council awarded the
design contract to Purkiss
·
Rose – RSI for $174,500. The preliminary design was
presented on September 26, 2000 and approved by Council. To
accommodate the increased scope of services, Council approved the
First Amendment to the contract on October 10, 2000 for
$79,345.
Analysis:
As a result of April 30, 2001 City Council
Workshop, the designer must redesign the Pier Head Plaza and
submit several different design concepts. The price for the
design work is $24,500 plus a $1,000 allowance for reproduction
and delivery costs. An increase of $25,500 for design services is
in order.
Under the terms of the existing agreement
between the City and Purkiss
·
Rose – RSI, the City has the option of ordering additional
services without changing the agreement. However, this must be
done by a written amendment approved by the City and the
Consultant. Please see Attachment No. 2.
This Second Amendment does not include
construction drawings, study models, presentation models,
artist’s renderings or perspectives, computer generated
graphics, construction estimates for alternate design concepts,
and materials boards.
Fiscal Impact
:
Sufficient funds are available in the project
account; therefore, no appropriation is required at this
time.
PROFESSIONAL SERVICES
AGREEMENT
SECOND amendment
Project No. CIP 00-630 Pier Renovation, Phase
III
THIS SECOND AMENDMENT to the Professional
Services Agreement between the City of Hermosa Beach and
Purkiss
·
Rose - RSI, made and entered into this 26
th
day of June 2001 at Hermosa Beach, County of Los Angeles,
State of California by and between the CITY OF HERMOSA BEACH,
through its duly elected, qualified and acting MAYOR,
hereinafter called the CITY, and the Purkiss
·
Rose - RSI, Inc., hereinafter called the CONSULTANT.
WHEREAS, City entered into a Professional
Services Agreement with Purkiss
·
Rose - RSI, Inc. on February 8, 2000 for the preparation of
detailed plans, specifications, cost estimates and other
construction documents for architectural upgrades to the Hermosa
Beach Municipal Pier; and
WHEREAS, City has determined the Project No.
CIP 00-630 will require additional professional services to
include design services;
NOW THEREFORE, in consideration of the
foregoing recitals and terms and conditions, the parties agree as
follows:
- Article I –
Scope of Work
is amended to read: "CONSULTANT shall perform all work
necessary to complete in a manner satisfactory to City the
services set forth in the Scope of Work in attached hereto as
Exhibit A and made part of this Second Amendment."
- Article II –
Costs
: "The CITY agrees to pay CONSULTANT for all the work or any
part of the work performed under this First Amendment at the
rates and in the manner established in Exhibit A.
Total expenditure made after this
contract shall not exceed the sum of $25,500 ($24,500 design
work plus $1,000 reproduction and delivery cost allowance).
This fee includes all expenses, consisting of all incidental
blueprinting, photography, travel and miscellaneous costs,
estimated to be accrued during the life of the contract. It
also includes any escalation or inflation factors anticipated.
No increase in fees will be allowed during the life of the
contract.
Any increase in contract amount of scope shall be by express
written amendment approved by the CITY and CONSULTANT.
ATTACHMENT 2
The CONSULTANT will be reimbursed
for costs incurred in the performance hereof as are allowable
under the provisions of Part 1-14 of the Federal Procurement
Regulations."
EXHIBIT A
scope of work:
-
One site plan which identifies the
general project changes requested by the Council including
the elimination of the stairway at the handicap ramp, the
modification of the curvilinear seating area, the removal
of raised planters and benches within the central plaza
area and the removal of the parking pad located at the
northern end of the central plaza.
- Four (4) colored conceptual paving layout design plans
for the central plaza area, three (3) colored conceptual
paving layout plans for upper plaza area and two (2) colored
conceptual paving layouts plans for the restroom building
hardscape area. The new conceptual layouts for the central
plaza, the upper plaza and the restroom building paving
designs will be coordinated to create a total of four (4)
overall paving design layouts for the project area.
- The colored design concepts for the alternate paving
design layout plans will be colored utilizing Ad Markers and
computer enhanced colors. The design concepts will not be
mounted.
- Development of one final site project plan identifying
the paving design layout approved the Council. The revised
site plan design exhibit will also include one revised plaza
cross section (colored) and two revised plaza elevations
(colored).
- Preparation of one final preliminary construction cost
estimate, which reflects the estimated costs of the final,
approved site and paving design.
This Change Order does not include the
following Services:
-
Construction Documents
-
Study Models or Presentation Models
-
Artist’s Renderings or
Perspectives
-
Computer Generated Graphics
-
Construction Cost Estimates for each
Alternate Design Concept.
-
Material Boards
The time line to complete the Alternate Design Concepts
identified in this Change Order Number Two will take
approximately five (5) weeks. This time line does not include the
time and scheduling for the City Council Presentations.
COSTS: