CIP PROJECT 96-624 NORTH PIER PARKING STRUCTURE
ACCEPTANCE
Recommendation:
It is recommended that the City Council:
- Accept the work by ARB, Inc. Constructors of Lake
Forest, California, for CIP Project No. 96-624, North Pier
Parking Structure.
- Authorize the Mayor to sign the Notice of
Completion.
- Authorize Staff to release payment to ARB, Inc.
Constructors (5% retained for 35 days following filing of
Notice of Completion).
- Authorize City Clerk to release ARB, Inc. Constructors
from the Faithful Performance Bond and the Labor and
Materials Bond.
Background
:
On September 22, 1999, City Council approved
entering into an agreement with ARB, Inc. Constructors to
construct the North Pier Parking Structure. The proposed work
included complete construction of a concrete parking structure
and appurtenances, demolition, excavation and grading, pile
driving, concrete floors, columns, beams, shearwalls, post
tension concrete slabs, electrical, mechanical, landscape and
civil improvements.
The contractor has completed the work to the
satisfaction of the Director of Public Works/City Engineer.
Analysis:
- The project was constructed according to the plans,
specifications and change orders prepared by Staff.
Therefore, Staff recommends acceptance of the work as
complete.
- The project was completed 21 days ahead of
schedule.
-
Start date: January 4, 1999
Contract time: 365 calendar days
Original completion date: January 4, 2000
Date of completion: December 14, 1999
- The project was completed within the appropriated
budget of $5,918,006.
Fiscal Impact:
-
Architectural Design/Engineering $
441,750
-
Construction Management $ 300,770
-
Construction Services $ 60,325
-
Miscellaneous $ 10,340
- Construction Cost $
5,026,285
- Total Project Cost $5,839,470
Funding:
- 121 Fund, Prop A Open Space $4,500,000
- 150 Fund, Hotel Developer Contribution $1,100,000
- 109 Fund, Downtown Enhancement Committee $
350,050
- Unexpended Project Balance $ 110,580