City of Hermosa Beach --- 01-26-99PROJECT NO. CIP 97-525 & CIP 98-526, COMMUNITY CENTER SKATE TRACK AND TENNIS COURT PROJECT - CONSTRUCTION MANAGEMENT SERVICES - APPROVE PROFESSIONAL SERVICE AGREEMENT
Recommendation:
It is recommended that the City Council:
Background:
The 1997-98 Capital Improvement Project Budget has included projects for the design and construction of the Community Centers' Skate Track and Tennis Courts. The design and bid phases of the projects have been completed and it is anticipated that the construction phase will be started in the very near future.
Construction management and inspection of public works construction contracts is a time consuming and demanding task, at best. Good construction management and inspection is essential to protect the interest of the public by assuring timely completion of the project within budget and in accordance with construction documents.
Staff has reviewed the construction management and inspection requirements for the Community Center projects and has determined that in order to complete the projects successfully, the services of a Construction Management firm are required.
Request for proposals (RFP) were sent to five reputable firms whom staff felt were capable of performing the services and would be interested in the project.
Proposals were received from the following firms:
Each proposal was evaluated on the basis of scope of services, fee and resumes of key personnel. The DMR Team, Inc. was selected.
The services will consist of, but not limited to the following:
Fiscal Impact:
In order to fund the proposed services, it will be necessary to appropriate $21,998, plus $2,200 to cover contingencies, from the 4% UUT Fund to the proposed contract. The current estimated balance in the fund is $605,728. After the additional appropriation of $24,198 the balance will be $581,530.
|
|