City of Hermosa Beach --- 04-25-00
PROJECT NO. 003-99 24th Street and Golden
Avenue–
Recommendation: It is recommended that the City Council:
Background: The 1999-2000 Street Maintenance/Traffic Safety Budget includes provisions for medium-size street repairs. Staff has combined the repair work for 24th Street with that of Golden Avenue. The plans, specifications and estimates for this work have been completed. The work to be performed consists of asphalt concrete street resurfacing, concrete reconstruction, curb & gutter and sidewalk reconstruction with minor drainage improvements. The plans, specifications and estimates are available in the office of the Director of Public Works/City Engineer for review.
Fiscal Impact: The engineer’s estimate for construction is $38,640. The actual bid price may be higher or lower than the engineer’s estimate. The current project budget is $25,000.
|
|