City of Hermosa Beach --- 06-09-98


EXTENSION OF EXISTING CONTRACT FOR

MUNICIPAL PIER CLEANING


Recommendation:


It is recommended that the City Council:


Continue the existing contract for performing Municipal Pier Cleaning.


Background:


The current contract for Municipal Pier cleaning expires on June 30, 1998. The FY 97/98 costs are $9,700. The Municipal Pier retrofit is scheduled for FY 98/99.


Analysis:


The Municipal Pier retrofit will require the pier to be closed down for 6-9 months. In addition, the building/restrooms at the end are scheduled to be removed. These actions impact the level of service needed. The actual closure may not involve all of the pier, so the pier head would still need service during the retrofit. There is also architectural upgrades tentatively scheduled for the fiscal years 99/2000.


Fiscal Impact:


The recommended FY 98-99 Budget has $5,000 allocated to the Municipal Pier Cleaning.


Alternatives:


1. Approve staff's recommendation and authorize staff to extend the existing contract on a month-to-month basis, with a reduction in expenditures as needed.


2. Instruct staff to develop new specifications and send it out for bids.