|
City of Hermosa Beach --- 10-26-99CIP PROJECT 98-621 PHASE III MUNICIPAL PIER ARCHITECTURAL UPGRADES – AWARD OF PROFESSIONAL SERVICES AGREEMENT FOR DESIGN
Recommendation : It is recommended that the City Council:
Summary :
On August 10, 1999, Council authorized Staff to enter into negotiation with Purkiss Rose – RSI to develop the final scope of services and design fee for the project, and return to Council with an agreement. Since the City has acquired valuable electronic data as well as other data in connection with the development of the Pier project, Staff negotiated for cost savings in the area of data collection for this phase of the project. Negotiations have been completed with no cost savings being achieved.
Background : This project is Phase III of a three-phase project that calls for the renovation of the pier. Phase III will include the plaza, lifeguard facilities and restroom improvements. Phase I, which called for the repair of the pier structure, was completed in May 1999. It is anticipated that Phase II, which consists of deck surface repair work, work related to the installation of a new lighting system and safety railing along the pier, will be completed in February 2000. The 1999-2000 Capital Improvement Project Budget includes funding for the design and construction of these proposed improvements.
The services of a consultant architect/engineer are needed to supplement the architectural/engineering capacity of the Public Works office. These services will include the preparation of detailed plans, specifications, cost estimates and other construction documents as required.
Staff sent out more than 50 RFP’s to firms Staff felt were qualified and would be interested in the project. Eight firms attended a non-mandatory pre-proposal briefing on July 8, 1999. Proposals were received from the following firms:
On August 3 rd the selection committee evaluated each proposal on the basis of the scope of services, similar projects, resumes of key personnel and work schedule. The committee consisted of City Staff members and a member of the County of Los Angeles Lifeguard Department.
Proposal Submittal Items:
After evaluating the above proposal data and presentation, the consulting firm of Purkiss Rose – RSI was chosen by the selection committee to provide the required services.
Analysis:
Data collection is a time consuming task and was a major cost factor during the project start-up phase. Since the City has acquired valuable electronic data as well as other data in connection with the development to the Pier project, Staff negotiated for cost savings in the area of data collection for this phase of the project. Negotiations have been completed with no savings being achieved.
The following is an excerpt from a letter received from Purkiss-Rose that gives a brief explanation why, from a building architectural standpoint, the consultant team cannot use the current plan data:
In addition: "From an electrical engineering standpoint, the plans were prepared thirty-five years ago and may not be the actual condition now. A thorough site investigation is needed to establish the present electrical site condition. An actual electrical load study is necessary to know whether the existing facility has enough capacity for the proposed additional loads or whether the existing service needs to be upgraded."
Further: "The other plans reflect an alternate design concept for the Pier Plaza area. Most of the drawings in this set of plans deal more with architectural and structural features of that particular design concept. However, there is one drawing that shows the existing utilities and Pier Plaza layout that may be of some use to our work. This base sheet would at the most save us some drafting and compilation of existing data. The problem is we either assume this data is correct or if we have to check this data for accuracy and completeness it would be the same as doing it ourselves in the first place."
In deference to time, Staff concurs with the above and recommends award to Purkiss-Rose RSI so that the project can now move forward without further delay. Fiscal Impact :
With a design fee of $174,500 and a contingency for $17,450, the proposed design budget is $191,950.
The total FY 99-00 budget for this project is $1,340,441 for design, engineering and construction; therefore no additional appropriation is required.
|
|||||||||||||||
|