City of Hermosa Beach --- 01-25-00CIP PROJECT 98-621 PHASE II MUNICIPAL PIER ARCHITECTURAL UPGRADES – AWARD CONSTRUCTION CONTRACT
Recommendation : It is recommended that the City Council:
Background : On November 9, 1999 the City Council authorized advertising for bids. The project was advertised in the Easy Reader, Green Sheet (Construction News Reporter), Daily Construction Service and Bid America. A total of twenty-two bid packages were picked up. The City Clerk received nine bids by the closing date of December 16, 1999. The bids were publicly opened and read aloud. The bid results are as follows:
Analysis: The price of the apparent low bidder, PKB Construction, is 12% below the engineer’s estimate of $1,314,867.00. A review of the bid documents revealed that PKB Construction is non-responsive for the following reasons: PKB construction proposed to sub-contract out 69% of the work. The contract documents call for the contractor to perform, with its own organization, work amounting to at least 50% of the contract price. Staff is of the opinion that the above is not an informality or an irregularity that may be waived. Therefore, staff is recommending that Los Angeles Engineering is the lowest responsible bidder. Los Angeles Engineering’s bid price is 11% lower than the engineer’s estimate. Staff has reviewed the low bidder documents and has found them to be in order and reference calls have been supportive of the contractors work habits.
Fiscal Impact : Funds from various sources * in the amount of $1,293,603 remain available for this project, CIP 98-621. Here is what is needed to complete the project:
Therefore an additional appropriation of $167,008 from fund 121 Prop A is required using funds remaining from other projects. Alternatives:
|
||||||||||||||||||||||||||||||
|