City of Hermosa Beach --- 02-23-99
CIP PROJECT NO. 96-508 HERMOSA BEACH GREENBELT - ACCEPTANCE
Recommendation:
It is recommended that the City Council:
Background:
On June 23, 1998, City Council approved entering into an agreement with Geoscene Landscape of Escondido to improve the Greenbelt in the amount of $586,502.25.
Improvements to the Greenbelt consisted of the following:
The contractor has completed the work to the satisfaction of the Director of Public Works/City Engineer.
Analysis:
Acceptance of the work as complete and final payment is in order. The project was constructed according to the plans and specifications prepared by the design contractor, Hirsch & Associates Inc. (formerly Heimberger Hirsch & Associates Inc.).
Original Contract Amount: $586,502.25
CCO No. 1 skimmer lines $ 5,600.00 - 0 days added CCO No. 2 saw blade $ 975.00 - 0 days added CCO No. 3 pavement $10,000.00 - 12 days added CCO No. 4 drinking fountain $ 4,174.50 - 0 days added CCO No. 5 block wall $ (7,950.00) - 2 days added CCO No. 6 concrete sidewalk w/drainage covert $ 2,434.00 - 2 days added CCO No. 7 tree trimming $ 6,045.00 - 0 days added CCO No. 8 fencing on top of upper ramp $ 8,452.50 - 7 days added CCO No. 9 change of railing diameter $ 0.00 - 17 days added CCO No. 10 guard rail at landing $ 0.00 - 7 days addedCCO No. 11 additional pavement $ 0.00 - 1 day added CCO No. 12 electrical for irrigation $ 0.00 - 14 days added CCO No. 13 reclaimed sign installation $ 0.00 - 2 days added
Contract Change Order Amount: $ 29,731.00
Quantity Adjustments: $ 23,839.16
Final Contract Amount: $640,072.41
The final Contract amount is 8.4% above the original contract amount.
Fiscal Impact:
The construction budget for this project is $692,314, therefore, no additional appropriation is required.