City of Hermosa Beach --- 10-10-00

PROJECT STATUS REPORT

 

Recommendation:

It is recommended that Council receive and file this report.

 

Summary:

This report gives the status of capital improvement projects that are either under design or construction. Capital improvement projects not indicated in this report can be found in the department’s Monthly Activity Report.

 

Project Status:

project no. cip 00-139 hermosa Ave., greenwich and manhattan ave. street improvements

description

completion date

   

preliminary engineering

completed

design & engineering (ps&e)

in progress

to council for approval to advertise

12-12-00

bid opening

1-25-01

to council for award

2-13-01

begin construction

3-19-01

end construction

5-25-01

 

project no. cip 99-144 strand bikeway & pedestrian walkway reconstruction between 24th and 35th street

description

completion date

   

preliminary engineering

completed

design & engineering (ps&e)

completed

to council for approval to advertise

completed

bid opening

10-12-00

to council for award

11-00

begin construction

01-01

end construction

04-01

 

project no. cip 95-150 hermosa avenue street improvements, between pier and 16th

description

completion date

   

preliminary engineering

completed

design & engineering (ps&e)

completed

to council for approval to advertise

completed

bid opening

completed

to council for award

completed

begin construction

in progress

end construction

11-07-00

 

project no. cip 99-305 installation of continuos deflection screen (cds) storm water clarifier units

description

completion date

   

preliminary engineering

completed

design & engineering (ps&e)

in progress

obtain permit from the county

11-24-00

to council for approval to advertise

12-12-00

bid opening

01-11-01

to council for award

01-01

begin construction

02-01

end construction

04-01

 

project no. cip 99-306 installation of catch basin inlet filters

description

completion date

   

preliminary engineering

completed

design & engineering (ps&e)

completed

to council for approval to advertise

completed

bid opening

completed

to council for award

complete

begin construction

in progress

end construction

11-06-00

   

 

project no. cip 00-410 loma area sewer and street improvements

description

completion date

   

preliminary engineering

completed

design & engineering (ps&e)

02-01

to council for approval to advertise

03-01

bid opening

04-01

to council for award

05-01

begin construction

06-01

end construction

01-02

 

project no. cip 95-507 valley park improvements

description

completion date

   

preliminary engineering

completed

design & engineering (ps&e)

in progress

to council for approval to advertise

01-30-01

bid opening

03-13-01

to council for award

04-10-01

begin construction

05-07-01

end construction

09-17-01

 

project no. cip 99-529 clark field improvements - ballfield backstop

description

completion date

   

preliminary engineering

completed

design & engineering (ps&e)

completed

to council for approval to advertise

10-10-00

bid opening

11-09-00

to council for award

11-28-00

begin construction

01-08-01

end construction

02-16-01

 

project no. cip 99-530 various park improvements - south park roller hockey

description

completion date

   

preliminary engineering

completed

design & engineering (ps&e)

in progress

to council for approval to advertise

11-14-00

bid opening

12-07-00

to council for award

01-09-00

begin construction

02-05-01

end construction

05-07-01

 

project no. cip 98-621 pier renovation, phase ii

description

completion date

   

preliminary engineering

completed

design & engineering (ps&e)

completed

to council for approval to advertise

completed

bid opening

completed

to council for award

completed

begin construction

completed

end construction

10-11-00

 

project no. cip 99-627 community center improvements - fencing

description

completion date

   

preliminary engineering

completed

design & engineering (ps&e)

in progress

to council for approval to advertise

11-14-00

bid opening

12-07-00

to council for award

01-09-01

begin construction

02-05-01

end construction

03-26-01

 

project no. cip 00-630 pier renovation, phase iii

description

completion date

   

preliminary engineering

completed

design & engineering (ps&e)

04-01

to council for approval to advertise

05-01

bid opening

08-01

to council for award

09-01

begin construction

10-01

end construction

10-02