City of Hermosa Beach --- 08-28-01

PROJECT STATUS REPORT

 

Recommendation:

It is recommended that Council receive and file this report.

Summary:

This report gives the status of capital improvement projects that are either under design or construction. Capital improvement projects not indicated in this report can be found in the department’s Monthly Activity Report.

Project Status :

project no. cip 00-139 hermosa avenue street improvements, 16th street to 26th street

description

status

preliminary engineering

completed 03-20-00

design & engineering (ps&e)

completed 03-13-01

to pw commission for review

n/a

to council for approval to advertise

completed 03-27-01

bid opening

completed 04-30-01

to council for award

completed 05-22-01

begin construction

07-09-01

end construction

09-01

project no. cip 01-159 hillcrest and rhodes, 18th st. to 21st street

description

status

preliminary engineering

08-01

design & engineering (ps&e)

12-01

to pw commission for review

01-02

to council for approval to advertise

02-02

bid opening

03-02

to council for award

03-02

begin construction

04-02

end construction

07-02

project no. cip 01-168 manhattan avenue, 27th st. to boundary

description

status

preliminary engineering

completed 3-20-00

design & engineering (ps&e)

completed 7-12-01

to pw commission for review

n/a

to council for approval to advertise

completed 7-24-01

bid opening

08-30-01

to council for award

09-11-01

begin construction

10-01

end construction

01-02

project no. cip 00-171 ardmore street improvements

description

status

preliminary engineering

completed 12-21-00

design & engineering (ps&e)

completed 02-15-01

to pw commission for review

completed 03-14-01

bid opening

completed 03-19-01

to council for award

completed 03-27-01

begin construction

07-09-01

end construction

10-01

project no. cip 00-172 21st street - valley to power street improvements

description

status

preliminary engineering

completed 12-21-00

design & engineering (ps&e)

completed 06-25-01

to pw commission for review

05-02-01, 7-11-01, 9-12-01

to council for approval to advertise

12-01

bid opening

01-02

to council for award

02-02

begin construction

03-02

end construction

05-02

project no. cip 01-191 14th street landscaped planters

description

status

preliminary engineering

02-01

design & engineering (ps&e)

12-01

to pw commission for review

10-01

to council for approval to advertise

01-02

bid opening

02-02

to council for award

03-02

begin construction

04-02

end construction

06-02

project no. cip 00-192 loma area street improvements

description

status

preliminary engineering

completed 03-08-00

design & engineering (ps&e)

10-01

to pw commission for review

12-01

to council for approval to advertise

02-02

bid opening

04-02

to council for award

05-02

begin construction

06-02

end construction

11-02

project no. cip 99-305 installation of continuos deflection screen (cds) storm water clarifier units

description

status

design & engineering (ps&e)

completed 11-20-00

obtain permit from the county – approval for proposed location pending

in progress

to pw commission for review

n/a

to council for approval to advertise

08-01

bid opening

09-01

to council for award

10-01

begin construction

11-01

end construction

02-02

project no. cip 99-306 installation of catch basin inlet filters

description

status

preliminary engineering/grant application

completed 11-24-98

design & engineering (ps&e)

completed 06-06-00

to pw commission for review

n/a

to council for approval to advertise

completed 06-13-00

bid opening

completed 06-29-00

to council for award (design/build)

completed 07-11-00

begin construction

08-01-01

end construction

completed 06-30-01

project no. cip 00-410 loma area sewer improvements

description

status

preliminary engineering

completed 03-08-00

design & engineering (ps&e)

10-01

to pw commission for review

11-01

to council for approval to advertise

12-01

bid opening

01-02

to council for award

02-02

begin construction

03-02

end construction

10-02

project no. cip 95-507 valley park improvements

description

status

preliminary engineering

completed 06-24-99

design & engineering (ps&e)

completed 03-05-01

to pw commission for review

n/a

to council for approval to advertise

03-27-01 back to staff

bid opening

tba

to council for award

tba

begin construction

tba

end construction

tba

project no. cip 99-529 clark field improvements

description

status

preliminary engineering

 

design & engineering (ps&e)

 

to pw commission for review

 

to council for approval to advertise

 

bid opening

 

to council for award

 

begin construction

 

end construction

 

project no. cip 01-531 3rd street park

description

status

preliminary engineering

completed 04-05-01

design & engineering (ps&e)

completed 05-01-01

to parks & recreation commission for review

completed 06-01-01

to public works commission for review

n/a

to council for approval to advertise

10-01

bid opening

11-01

to council for award

12-01

begin construction

01-02

end construction

03-02

project no. cip 01-532 south park hockey rink improvements

description

status

preliminary engineering

completed 05-08-00

design & engineering (ps&e)

completed 10-23-00

to pw commission for review

n/a

to council for approval to advertise

completed 11-28-00

bid opening

completed 12-07-00

to council for approval to re-bid

completed 02-27-01

bid opening

completed 07-24-01

to council for award

08-01

begin construction

09-01

end construction

11-01

project no. cip 95-622 city hall remodel – ada upgrades

description

status

preliminary engineering

completed

design & engineering (ps&e)

in progress

to pw commission for review

n/a

cm agreement to council for approval

completed 11-28-00

constructibility review

in progress

relocation programming

in progress

to council for approval of plans & specs, advertise

completed 05-22-01

bid opening

completed 07-12-01

to council for award

08-28-01

begin construction

10-01

end construction

06-02

project no. cip 99-627 community center improvements - fencing

description

status

preliminary engineering

completed 05-08-00

design & engineering (ps&e)

completed 10-23-00

to pw commission for review

n/a

to council for approval to advertise

completed 11-14-00

bid opening

completed 12-07-00

to council for award

completed 01-09-01

begin construction

completed 03-12-01

end construction

completed 06-30-01

project no. cip 01-628 community center courtyard and painting

description

status

preliminary engineering

completed 04-09-01

design & engineering (ps&e)

completed 06-14-01

to pw commission for review

n/a

to council for approval to advertise

completed 07-24-01

bid opening

08-01

to council for award

09-01

begin construction

09-01

end construction

12-01

project no. cip 00-630 pier renovation, phase iii

description

status

preliminary engineering

completed 03-08-00

design & engineering (ps&e)

12-01

to pw commission for review

01-02

to council for approval to advertise

01-02

bid opening

04-02

to council for award

04-02

begin construction

05-02

end construction

06-03

Indicates Construction Completed