Recommendation:
It is recommended that Council receive and file this report.
Summary:
This report gives the status of capital improvement projects that are either under design or construction.  Capital improvement projects not indicated in this report can be found in the department's Monthly Activity Report.
Project Status:
PROJECT NO. CIP 02-108 STREET IMPROVEMENTS - 2ND ST. FROM PCH TO THE STRAND; MONTEREY FROM HERONDO TO 4TH ST.
 
  | DESCRIPTION | STATUS | 
 
 
   | REVISED | 
 
 
| PRELIMINARY ENGINEERING | COMPLETED     05/07/03 | 
 
| DESIGN & ENGINEERING (PS&E) | 07/03 | 
 
| TO PW COMMISSION FOR REVIEW | 08/03 | 
 
| TO COUNCIL FOR APPROVAL TO ADVERTISE | 09/03 | 
 
| BID OPENING | 10/03 | 
 
| TO COUNCIL FOR AWARD | 11/03 | 
 
| BEGIN CONSTRUCTION | 12/03 | 
 
| END CONSTRUCTION | 02/04 | 
PROJECT NO. CIP 00-140 11TH PLACE ON-STREET PARKING IMPROVEMENTS
 
  | DESCRIPTION | STATUS | 
 
 
   | REVISED | 
 
 
| PRELIMINARY ENGINEERING | COMPLETED 12/22/02 | 
 
| UNDERGROUNDING DESIGN BY SCE | 09/03 | 
 
| PLANS SPECS & ESTIMATES | 10/03 | 
 
| TO PW COMMISSION FOR REVIEW | 10/03 | 
 
| TO COUNCIL FOR APPROVAL TO ADVERTISE | 11/03 | 
 
| BID OPENING | 12/03 | 
 
| TO COUNCIL FOR AWARD | 02/04 | 
 
| BEGIN CONSTRUCTION | 03/04 | 
 
| END CONSTRUCTION | 04/05 | 
PROJECT NO. CIP 02-147 CURB-CUTS/HANDICAP RAMPS
 
  | DESCRIPTION | STATUS | 
 
 
   | REVISED | 
 
 
| PRELIMINARY ENGINEERING | COMPLETED     09/15/02 | 
 
| DESIGN & ENGINEERING (PS&E) | BEING REVIEWED BY COUNTY | 
 
| TO PW COMMISSION FOR REVIEW | N/A | 
 
| TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A | 
 
| BID OPENING | COMPLETED     04/10/03 | 
 
| TO COUNCIL FOR AWARD | COMPLETED     04/22/03 | 
 
| BEGIN CONSTRUCTION | 07/03 | 
 
| END CONSTRUCTION | 09/03 | 
PROJECT NO. CIP 01-159 HILLCREST AND RHODES, 18TH ST. TO 21ST STREET
 
  | DESCRIPTION | STATUS | 
 
 
   | REVISED | 
 
 
| PRELIMINARY ENGINEERING | COMPLETED     08-09-01 | 
 
| DESIGN & ENGINEERING (PS&E) | COMPLETED     05-16-02 | 
 
| TO PW COMMISSION FOR REVIEW | COMPLETED      01/16/02; 3/20/02 | 
 
| TO COUNCIL FOR APPROVAL TO ADVERTISE | COMPLETED     09/10/02 | 
 
| BID OPENING | COMPLETED     10/17/02 | 
 
| TO COUNCIL FOR AWARD | COMPLETED     11/12/02 | 
 
| BEGIN CONSTRUCTION | COMPLETED     01/21/03 | 
 
| END CONSTRUCTION |  07/03 | 
PROJECT NO. CIP 01-174 ARTESIA BOULEVARD IMPROVEMENTS - PCH TO HARPER
 
  | DESCRIPTION | STATUS | 
 
 
   | REVISED | 
 
 
| PRELIMINARY ENGINEERING | COMPLETED     12/23/03  | 
 
| DESIGN & ENGINEERING (PS&E) | COMPLETED     04/03 | 
 
| TO PW COMMISSION FOR REVIEW | N/A - MULTI-CITY REVIEW | 
 
| TO COUNCIL FOR APPROVAL OF AGREEMENT | COMPLETED     04/22/03 | 
 
| BID OPENING | N/A | 
 
| TO COUNCIL FOR AWARD | COMPLETED      05/06/03 REDONDO BEACH  CC | 
 
| BEGIN CONSTRUCTION | 06/03 - REDONDO; 09/03 - HERMOSA | 
 
| END CONSTRUCTION | 12/03 | 
PROJECT NO. CIP 02-185 5TH STREET - PCH TO ARDMORE ;PCH TO PROSPECT AND GENTRY
 
  | DESCRIPTION | STATUS | 
 
 
   | REVISED | 
 
 
| PRELIMINARY ENGINEERING | COMPLETED     12/23/03  | 
 
| DESIGN & ENGINEERING (PS&E) | 07/03 | 
 
| TO PW COMMISSION FOR REVIEW | COMPLETED      05/28/03 | 
 
| TO COUNCIL FOR APPROVAL TO ADVERTISE | 08/03 | 
 
| BID OPENING | 09/03 | 
 
| TO COUNCIL FOR AWARD | 10/03 | 
 
| BEGIN CONSTRUCTION | 12/03 | 
 
| END CONSTRUCTION | 02/04 | 
Projects 02-185 and 02-187 have been combined into a single project.
PROJECT NO. CIP 02-189 MYRTLE AREA STREET IMPROVEMENTS
 
  | DESCRIPTION | STATUS | 
 
 
   | REVISED | 
 
 
| PRELIMINARY ENGINEERING | COMPLETED  9/12/02 | 
 
| DESIGN & ENGINEERING (PS&E) | 07/03 | 
 
| TO PW COMMISSION FOR REVIEW | COMPLETED  3/19/03 | 
 
| TO COUNCIL FOR APPROVAL TO ADVERTISE | 07/03 | 
 
| BID OPENING | 08/03 | 
 
| TO COUNCIL FOR AWARD | 08/03 | 
 
| BEGIN CONSTRUCTION | 09/03 | 
 
| END CONSTRUCTION | 11/03 | 
PROJECT NO. CIP 00-192 LOMA AREA STREET IMPROVEMENTS
 
  | DESCRIPTION | STATUS | 
 
 
   | REVISED | 
 
 
| PRELIMINARY ENGINEERING | COMPLETED     03/08/00 | 
 
| DESIGN & ENGINEERING (PS&E) | COMPLETED     11/05/02 | 
 
| TO PW COMMISSION FOR REVIEW | COMPLETED     12/13/00 | 
 
| TO COUNCIL FOR APPROVAL TO ADVERTISE | COMPLETED     11/12/02 | 
 
| BID OPENING | COMPLETED     12/12/02 | 
 
| TO COUNCIL FOR AWARD | COMPLETED     01/14/03 | 
 
| BEGIN CONSTRUCTION | COMPLETED     03/10/03 | 
 
| END CONSTRUCTION | 08/03 | 
PROJECT NO. CIP 02-193 VARIOUS STREET IMPROVEMENTS #4
 
  | DESCRIPTION | STATUS | 
 
 
   | REVISED | 
 
 
| PRELIMINARY ENGINEERING | PROJECT ON HOLD | 
 
| DESIGN & ENGINEERING (PS&E) | 
 
| TO PW COMMISSION FOR REVIEW | 
 
| TO COUNCIL FOR APPROVAL TO ADVERTISE | 
 
| BID OPENING | 
 
| TO COUNCIL FOR AWARD | 
 
| BEGIN CONSTRUCTION | 
 
| END CONSTRUCTION | 
PROJECT NO. CIP 99-409 MANHOLE REPAIR/RECONSTRUCTION
 
  | DESCRIPTION | STATUS | 
 
 
| PRELIMINARY ENGINEERING | N/A | 
 
| DESIGN & ENGINEERING (PS&E) | N/A | 
 
| TO PW COMMISSION FOR REVIEW | N/A | 
 
| TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A | 
 
| BID OPENING | COMPLETED      06/12/03 | 
 
| TO COUNCIL FOR AWARD | 07/03 | 
 
| BEGIN CONSTRUCTION | 07/03 | 
 
| END CONSTRUCTION | 09/03 | 
PROJECT NO. CIP 00-410 SEWER REHABILITATION - LOMA AREA
 
  | DESCRIPTION | STATUS | 
 
 
   | REVISED | 
 
 
| PRELIMINARY ENGINEERING | COMPLETED     03/08/00 | 
 
| DESIGN & ENGINEERING (PS&E) | COMPLETED     11/05/02 | 
 
| TO PW COMMISSION FOR REVIEW | COMPLETED     12/13/00 | 
 
| TO COUNCIL FOR APPROVAL TO ADVERTISE | COMPLETED     11/12/02 | 
 
| BID OPENING | COMPLETED     12/12/02 | 
 
| TO COUNCIL FOR AWARD | COMPLETED     01/14/03 | 
 
| BEGIN CONSTRUCTION | COMPLETED     03/10/03 | 
 
| END CONSTRUCTION | 08/03 | 
PROJECT NO. CIP 00-411 SEWER REHABILITATION, AREA 1
 
  | DESCRIPTION | STATUS | 
 
 
   | REVISED | 
 
 
| PRELIMINARY ENGINEERING | COMPLETED     3/27/02 | 
 
| DESIGN & ENGINEERING (PS&E) | COMPLETED     11/05/02 | 
 
| TO PW COMMISSION FOR REVIEW | N/A | 
 
| TO COUNCIL FOR APPROVAL TO ADVERTISE | COMPLETED     11/12/02 | 
 
| BID OPENING | COMPLETED     12/12/02 | 
 
| TO COUNCIL FOR AWARD | COMPLETED     01/14/03 | 
 
| BEGIN CONSTRUCTION | COMPLETED     02/24/03 | 
 
| END CONSTRUCTION | 08/03 | 
PROJECT NO. CIP 95-507 VALLEY PARK IMPROVEMENTS
 
  | DESCRIPTION | STATUS | 
 
 
| PRELIMINARY ENGINEERING | COMPLETED     06-24-99 | 
 
| DESIGN & ENGINEERING (PS&E) | COMPLETED     03-05-01 | 
 
| TO PW COMMISSION FOR REVIEW | N/A | 
 
| TO COUNCIL FOR APPROVAL TO ADVERTISE | 3/27/01 BACK TO STAFF; COMPLETED 2/25/02 | 
 
| BID OPENING | COMPLETED     4/18/02 | 
 
| TO COUNCIL FOR AWARD | COMPLETED     6/25/02 | 
 
| BEGIN CONSTRUCTION | COMPLETED     9/03/02 | 
 
| END CONSTRUCTION | 5/22/03 - PUNCH LIST ITEMS & MAINTENANCE REMAIN | 
PROJECT NO. CIP 02-626 COMMUNITY CENTER THEATER ADA UPGRADES
 
  | DESCRIPTION | STATUS | 
 
 
   | 8/26/02 ON HOLD PER S. BLUMENFELD | 
 
 
| PRELIMINARY ENGINEERING | COMPLETED     08/12/02  | 
 
| DESIGN & ENGINEERING (PS&E) | COMPLETED      03/03/03 | 
 
| TO PW COMMISSION FOR REVIEW | N/A | 
 
| TO COUNCIL FOR APPROVAL TO ADVERTISE | 07/03 | 
 
| BID OPENING | 08/03 | 
 
| TO COUNCIL FOR AWARD | 09/03 | 
 
| BEGIN CONSTRUCTION | 10/03 | 
 
| END CONSTRUCTION | 12/03 | 
PROJECT NO. CIP 00-630 PIER RENOVATION, PHASE III
 
  | DESCRIPTION | STATUS | 
 
 
   | REVISED | 
 
 
| PRELIMINARY ENGINEERING | COMPLETED     03-08-00 | 
 
| DESIGN & ENGINEERING (PS&E) | 07/03 | 
 
| TO PW COMMISSION FOR REVIEW | N/A | 
 
| TO COUNCIL FOR APPROVAL TO ADVERTISE | COMPLETED 05/27/03 | 
 
| BID OPENING | 08/03 | 
 
| TO COUNCIL FOR AWARD | 09/03 | 
 
| BEGIN CONSTRUCTION | 10/03 | 
 
| END CONSTRUCTION | 10/04 | 
PROJECT NO. CIP 01-633 CITY BUILDINGS - RE-ROOFING
 
  | DESCRIPTION | STATUS | 
 
 
   | PROJECT ON HOLD | 
 
 
| PRELIMINARY ENGINEERING | N/A | 
 
| DESIGN & ENGINEERING (PS&E) | 
 
| TO PW COMMISSION FOR REVIEW | 
 
| TO COUNCIL FOR APPROVAL TO ADVERTISE | 
 
| BID OPENING | 
 
| TO COUNCIL FOR AWARD | 
 
| BEGIN CONSTRUCTION | 
 
| END CONSTRUCTION | 
PROJECT NO. CIP 02-634 CITY BUILDINGS - EXTERIOR PAINTING
 
  | DESCRIPTION | STATUS | 
 
 
   | PROJECT ON HOLD | 
 
 
| PRELIMINARY ENGINEERING | N/A | 
 
| DESIGN & ENGINEERING (PS&E) | 
 
| TO PW COMMISSION FOR REVIEW | 
 
| TO COUNCIL FOR APPROVAL TO ADVERTISE | 
 
| BID OPENING | 
 
| TO COUNCIL FOR AWARD | 
 
| BEGIN CONSTRUCTION | 
 
| END CONSTRUCTION | 
* TBD - TO BE DETERMINED