Project Status:

PROJECT NO. CIP 02-108 STREET IMPROVEMENTS - 2ND ST. FROM PCH TO THE STRAND; MONTEREY FROM HERONDO TO 4TH ST.

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 05/07/03
DESIGN & ENGINEERING (PS&E)12/03
TO PW COMMISSION FOR REVIEW01/04
TO COUNCIL FOR APPROVAL TO ADVERTISE02/04
BID OPENING03/04
TO COUNCIL FOR AWARD04/04
BEGIN CONSTRUCTION06/04
END CONSTRUCTION07/04

PROJECT NO. CIP 00-140 11TH PLACE ON-STREET PARKING IMPROVEMENTS

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 12/22/02
UNDERGROUNDING DESIGN BY SCE12/03
PLANS SPECS & ESTIMATES12/03
TO PW COMMISSION FOR REVIEWCOMPLETED 10/22/03
TO COUNCIL FOR APPROVAL TO ADVERTISE12/03
BID OPENING01/04
TO COUNCIL FOR AWARD02/04
BEGIN CONSTRUCTION03/04
END CONSTRUCTION04/05

PROJECT NO. CIP 02-147 CURB-CUTS/HANDICAP RAMPS

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 09/15/02
DESIGN & ENGINEERING (PS&E)REVIEWED BY COUNTY
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 04/10/03
TO COUNCIL FOR AWARDCOMPLETED 04/22/03
BEGIN CONSTRUCTIONCOMPLETED 07/07/03
END CONSTRUCTIONCOMPLETED 12/09/03

PROJECT NO. CIP 01-174 ARTESIA BOULEVARD IMPROVEMENTS - PCH TO HARPER

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 12/23/03
DESIGN & ENGINEERING (PS&E)COMPLETED 04/03
TO PW COMMISSION FOR REVIEWN/A - MULTI-CITY REVIEW
TO COUNCIL FOR APPROVAL OF AGREEMENTCOMPLETED 04/22/03
BID OPENINGN/A
TO COUNCIL FOR AWARDCOMPLETED 05/06/03 REDONDO BEACH CC
BEGIN CONSTRUCTION06/03 - REDONDO; 09/29/03 - HERMOSA
END CONSTRUCTION12/03

PROJECT NO. CIP 02-185 5TH STREET - PCH TO ARDMORE ;PCH TO PROSPECT AND GENTRY

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 12/23/03
DESIGN & ENGINEERING (PS&E)COMPLETED 08/11/03
TO PW COMMISSION FOR REVIEWCOMPLETED 05/28/03
TO COUNCIL FOR APPROVAL TO ADVERTISECOMPLETED 08/12/03
BID OPENINGBEING RE-BID - OPENING 11/20/03
TO COUNCIL FOR AWARD01/04
BEGIN CONSTRUCTION02/04
END CONSTRUCTION04/04

Projects 02-185 and 02-187 have been combined into a single project.

PROJECT NO. CIP 02-189 MYRTLE AREA STREET IMPROVEMENTS

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 9/12/02
DESIGN & ENGINEERING (PS&E)COMPLETED 7/07/03
TO PW COMMISSION FOR REVIEWCOMPLETED 3/19/03
TO COUNCIL FOR APPROVAL TO ADVERTISECOMPLETED 9/23/03
BID OPENINGCOMPLETED 10/30/03
TO COUNCIL FOR AWARD11/12/03
BEGIN CONSTRUCTION01/04
END CONSTRUCTION03/04

PROJECT NO. CIP 00-192 LOMA AREA STREET IMPROVEMENTS

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 03/08/00
DESIGN & ENGINEERING (PS&E)COMPLETED 11/05/02
TO PW COMMISSION FOR REVIEWCOMPLETED 12/13/00
TO COUNCIL FOR APPROVAL TO ADVERTISECOMPLETED 11/12/02
BID OPENINGCOMPLETED 12/12/02
TO COUNCIL FOR AWARDCOMPLETED 01/14/03
BEGIN CONSTRUCTIONCOMPLETED 03/10/03
END CONSTRUCTION10/13/03 ONLY PUNCH LIST ITEMS REMAIN

PROJECT NO. CIP 02-193 VARIOUS STREET IMPROVEMENTS #4

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGPROJECT ON HOLD
DESIGN & ENGINEERING (PS&E)
TO PW COMMISSION FOR REVIEW
TO COUNCIL FOR APPROVAL TO ADVERTISE
BID OPENING
TO COUNCIL FOR AWARD
BEGIN CONSTRUCTION
END CONSTRUCTION

PROJECT NO. CIP 99-409 MANHOLE REPAIR/RECONSTRUCTION

DESCRIPTIONSTATUS
PRELIMINARY ENGINEERINGN/A
DESIGN & ENGINEERING (PS&E)N/A
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 06/12/03 WILL BE REBID
TO COUNCIL FOR AWARDTO BE DETERMINED
BEGIN CONSTRUCTIONTO BE DETERMINED
END CONSTRUCTIONTO BE DETERMINED

PROJECT NO. CIP 00-410 SEWER REHABILITATION - LOMA AREA

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 03/08/00
DESIGN & ENGINEERING (PS&E)COMPLETED 11/05/02
TO PW COMMISSION FOR REVIEWCOMPLETED 12/13/00
TO COUNCIL FOR APPROVAL TO ADVERTISECOMPLETED 11/12/02
BID OPENINGCOMPLETED 12/12/02
TO COUNCIL FOR AWARDCOMPLETED 01/14/03
BEGIN CONSTRUCTIONCOMPLETED 03/10/03
END CONSTRUCTION10/13/03 ONLY PUNCH LIST ITEMS REMAIN

PROJECT NO. CIP 00-411 SEWER REHABILITATION, AREA 1

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 3/27/02
DESIGN & ENGINEERING (PS&E)COMPLETED 11/05/02
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISECOMPLETED 11/12/02
BID OPENINGCOMPLETED 12/12/02
TO COUNCIL FOR AWARDCOMPLETED 01/14/03
BEGIN CONSTRUCTIONCOMPLETED 02/24/03
END CONSTRUCTION10/13/03 ONLY PUNCH LIST ITEMS REMAIN

PROJECT NO. CIP 02-626 COMMUNITY CENTER THEATER ADA UPGRADES

DESCRIPTIONSTATUS
8/26/02 ON HOLD PER S. BLUMENFELD
PRELIMINARY ENGINEERINGCOMPLETED 08/12/02
DESIGN & ENGINEERING (PS&E)COMPLETED 03/03/03
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISECOMPLETED 07/08/03
BID OPENINGCOMPLETED 11/05/03
TO COUNCIL FOR AWARDCOMPLETED 11/12/03
BEGIN CONSTRUCTIONSTARTED 12/01/03
END CONSTRUCTION02/04

PROJECT NO. CIP 00-630 PIER RENOVATION, PHASE III

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 03/08/00
DESIGN & ENGINEERING (PS&E)COMPLETED 08/29/03
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISECOMPLETED 05/27/03
BID OPENINGCOMPLETED 10-30-03 TO BE RE-BID
TO COUNCIL FOR AWARDTBD
BEGIN CONSTRUCTIONTBD
END CONSTRUCTIONTBD

PROJECT NO. CIP 01-633 CITY BUILDINGS - RE-ROOFING

DESCRIPTIONSTATUS
PRELIMINARY ENGINEERINGTBD
DESIGN & ENGINEERING (PS&E)
TO PW COMMISSION FOR REVIEW
TO COUNCIL FOR APPROVAL TO ADVERTISE
BID OPENING
TO COUNCIL FOR AWARD
BEGIN CONSTRUCTION
END CONSTRUCTION

PROJECT NO. CIP 02-634 CITY BUILDINGS - EXTERIOR PAINTING

DESCRIPTIONSTATUS
PRELIMINARY ENGINEERINGTBD
DESIGN & ENGINEERING (PS&E)
TO PW COMMISSION FOR REVIEW
TO COUNCIL FOR APPROVAL TO ADVERTISE
BID OPENING
TO COUNCIL FOR AWARD
BEGIN CONSTRUCTION
END CONSTRUCTION

* TBD - TO BE DETERMINED