Project Status Report January 2004

Recommendation:

It is recommended that Council receive and file this report.

Summary:

This report gives the status of capital improvement projects that are either under design or construction. Capital improvement projects not indicated in this report can be found in the department's Monthly Activity Report.

Project Status:

PROJECT NO. CIP 02-108 STREET IMPROVEMENTS - 2ND ST. FROM PCH TO THE STRAND; MONTEREY FROM HERONDO TO 4TH ST.

DESCRIPTIONSTATUS
PROJECT ON HOLD
PRELIMINARY ENGINEERINGCOMPLETED 05/07/03
DESIGN & ENGINEERING (PS&E)
TO PW COMMISSION FOR REVIEW
TO COUNCIL FOR APPROVAL TO ADVERTISE
BID OPENING
TO COUNCIL FOR AWARD
BEGIN CONSTRUCTION
END CONSTRUCTION

PROJECT NO. CIP 00-140 11TH PLACE ON-STREET PARKING IMPROVEMENTS

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 12/22/02
UNDERGROUNDING DESIGN BY SCE02/04
PLANS SPECS & ESTIMATES02/04
TO PW COMMISSION FOR REVIEWCOMPLETED 10/22/03
TO COUNCIL FOR APPROVAL TO ADVERTISE03/04
BID OPENING04/04
TO COUNCIL FOR AWARD05/04
BEGIN CONSTRUCTION06/04
END CONSTRUCTION07/05

PROJECT NO. CIP 02-185 5TH STREET - PCH TO ARDMORE ;PCH TO PROSPECT

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 12/23/03
DESIGN & ENGINEERING (PS&E)COMPLETED 08/11/03
TO PW COMMISSION FOR REVIEWCOMPLETED 05/28/03
TO COUNCIL FOR APPROVAL TO ADVERTISECOMPLETED 08/12/03
BID OPENINGBEING RE-BID - OPENING 11/20/03
TO COUNCIL FOR AWARDCOMPLETED 01/13/04
BEGIN CONSTRUCTION03/04
END CONSTRUCTION054/04

Projects 02-185 and 02-187 have been combined into a single project.

PROJECT NO. CIP 02-189 MYRTLE AREA STREET IMPROVEMENTS

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 9/12/02
DESIGN & ENGINEERING (PS&E)COMPLETED 7/07/03
TO PW COMMISSION FOR REVIEWCOMPLETED 3/19/03
TO COUNCIL FOR APPROVAL TO ADVERTISECOMPLETED 9/23/03
BID OPENINGCOMPLETED 10/30/03
TO COUNCIL FOR AWARDCOMPLETED 11/12/03
BEGIN CONSTRUCTIONSTARTED 01/05/04
END CONSTRUCTION03/04

PROJECT NO. CIP 00-192 LOMA AREA STREET IMPROVEMENTS

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 03/08/00
DESIGN & ENGINEERING (PS&E)COMPLETED 11/05/02
TO PW COMMISSION FOR REVIEWCOMPLETED 12/13/00
TO COUNCIL FOR APPROVAL TO ADVERTISECOMPLETED 11/12/02
BID OPENINGCOMPLETED 12/12/02
TO COUNCIL FOR AWARDCOMPLETED 01/14/03
BEGIN CONSTRUCTIONCOMPLETED 03/10/03
END CONSTRUCTION10/13/03 ONLY PUNCH LIST ITEMS REMAIN

PROJECT NO. CIP 02-193 VARIOUS STREET IMPROVEMENTS #4

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGPROJECT ON HOLD
DESIGN & ENGINEERING (PS&E)
TO PW COMMISSION FOR REVIEW
TO COUNCIL FOR APPROVAL TO ADVERTISE
BID OPENING
TO COUNCIL FOR AWARD
BEGIN CONSTRUCTION
END CONSTRUCTION

PROJECT NO. CIP 99-409 MANHOLE REPAIR/RECONSTRUCTION

DESCRIPTIONSTATUS
PRELIMINARY ENGINEERINGN/A
DESIGN & ENGINEERING (PS&E)N/A
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 06/12/03 WILL BE REBID
TO COUNCIL FOR AWARDTO BE DETERMINED
BEGIN CONSTRUCTIONTO BE DETERMINED
END CONSTRUCTIONTO BE DETERMINED

PROJECT NO. CIP 00-410 SEWER REHABILITATION - LOMA AREA

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 03/08/00
DESIGN & ENGINEERING (PS&E)COMPLETED 11/05/02
TO PW COMMISSION FOR REVIEWCOMPLETED 12/13/00
TO COUNCIL FOR APPROVAL TO ADVERTISECOMPLETED 11/12/02
BID OPENINGCOMPLETED 12/12/02
TO COUNCIL FOR AWARDCOMPLETED 01/14/03
BEGIN CONSTRUCTIONCOMPLETED 03/10/03
END CONSTRUCTION10/13/03 ONLY PUNCH LIST ITEMS REMAIN

PROJECT NO. CIP 00-411 SEWER REHABILITATION, AREA 1

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 3/27/02
DESIGN & ENGINEERING (PS&E)COMPLETED 11/05/02
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISECOMPLETED 11/12/02
BID OPENINGCOMPLETED 12/12/02
TO COUNCIL FOR AWARDCOMPLETED 01/14/03
BEGIN CONSTRUCTIONCOMPLETED 02/24/03
END CONSTRUCTION10/13/03 ONLY PUNCH LIST ITEMS REMAIN

PROJECT NO. CIP 02-626 COMMUNITY CENTER THEATER ADA UPGRADES

DESCRIPTIONSTATUS
8/26/02 ON HOLD PER S. BLUMENFELD
PRELIMINARY ENGINEERINGCOMPLETED 08/12/02
DESIGN & ENGINEERING (PS&E)COMPLETED 03/03/03
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISECOMPLETED 07/08/03
BID OPENINGCOMPLETED 11/05/03
TO COUNCIL FOR AWARDCOMPLETED 11/12/03
BEGIN CONSTRUCTIONSTARTED 12/01/03
END CONSTRUCTION03/04

PROJECT NO. CIP 00-630 PIER RENOVATION, PHASE III

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 03/08/00
DESIGN & ENGINEERING (PS&E)COMPLETED 08/29/03
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISECOMPLETED 05/27/03
BID OPENINGCOMPLETED 10/30/03 TO BE RE-BID
TO COUNCIL FOR AWARDTBD
BEGIN CONSTRUCTIONTBD
END CONSTRUCTIONTBD

PROJECT NO. CIP 01-633 CITY BUILDINGS - RE-ROOFING

DESCRIPTIONSTATUS
PRELIMINARY ENGINEERINGTBD
DESIGN & ENGINEERING (PS&E)
TO PW COMMISSION FOR REVIEW
TO COUNCIL FOR APPROVAL TO ADVERTISE
BID OPENING
TO COUNCIL FOR AWARD
BEGIN CONSTRUCTION
END CONSTRUCTION

PROJECT NO. CIP 02-634 CITY BUILDINGS - EXTERIOR PAINTING

DESCRIPTIONSTATUS
PRELIMINARY ENGINEERINGTBD
DESIGN & ENGINEERING (PS&E)
TO PW COMMISSION FOR REVIEW
TO COUNCIL FOR APPROVAL TO ADVERTISE
BID OPENING
TO COUNCIL FOR AWARD
BEGIN CONSTRUCTION
END CONSTRUCTION

* TBD - TO BE DETERMINED