Project Status Report February 2007

Recommendation:

It is recommended that Council receive and file this report.

Summary:

This report gives the status of capital improvement projects that are either under design or construction. Capital improvement projects not indicated in this report can be found in the department's Monthly Activity Report.

Project Status:

PROJECT NO. CIP 02-104 BAYVIEW POST-UNDERGROUNDING STREET IMPROVEMENTS – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 12/09/05
DESIGN & ENGINEERING (PS&E)COMPLETED 01/12/07
TO COUNCIL FOR APPROVAL TO ADVERTISETBD
BID OPENINGTBD
TO COUNCIL FOR AWARDTBD
BEGIN CONSTRUCTION3RD QTR FY 06-07 EST.
END CONSTRUCTIONTBD

PROJECT NO. CIP 02-106 BEACH DRIVE POST-UNDERGROUNDING STREET IMPROVEMENTS – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 03-10-05
DESIGN & ENGINEERING (PS&E)COMPLETED 11/08/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGN/A
TO COUNCIL FOR AWARD10/24/06 ADDED TO OTHER CIP PROJECT
BEGIN CONSTRUCTIONCOMPLETED 01/08/07
END CONSTRUCTIONCOMPLETED 1/26/07

PROJECT NO. CIP 05-109 CONCRETE ROAD RECONSTRUCTION – VARIOUS LOCATIONS – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
 
PRELIMINARY ENGINEERINGCOMPLETED 04/06
DESIGN & ENGINEERING (PS&E)COMPLETED 04/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 05/15/06
TO COUNCIL FOR AWARDCOMPLETED 06/13/06
BEGIN CONSTRUCTIONCOMPLETED 07/24/06
END CONSTRUCTIONCOMPLETED 12/22/06

PROJECT NO. CIP 05-110 SLURRY/CRACK SEALING AT VARIOUS LOCATIONS – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 10/20/05
DESIGN & ENGINEERING (PS&E)COMPLETED 04/12/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 10/12/06
TO COUNCIL FOR AWARD11/14/06
BEGIN CONSTRUCTION03/07
END CONSTRUCTION03/07

PROJECT NO. CIP 04-112 STREET IMPROVEMENTS – SLURRY SEAL AT VARIOUS LOCATIONS – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 03/04/05
DESIGN & ENGINEERING (PS&E)COMPLETED 04/12/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 10/12/06
TO COUNCIL FOR AWARD11/14/06
BEGIN CONSTRUCTIONCOMPLETED 03/26/07
END CONSTRUCTION03/07

PROJECT NO. CIP 04-116 STREET IMPROVEMENTS – PIER AVE., HERMOSA AVE. TO PCH – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGTBD
DESIGN & ENGINEERING (PS&E)TBD
TO PW COMMISSION FOR REVIEWTBD
TO COUNCIL FOR APPROVAL TO ADVERTISETBD
BID OPENINGTBD
TO COUNCIL FOR AWARDTBD
BEGIN CONSTRUCTIONTBD
END CONSTRUCTIONTBD

PROJECT NO. CIP 04-117 STREET IMPROVEMENTS – MANHATTAN AVE. 1ST ST. TO CITY LIMITS – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 04/06
DESIGN & ENGINEERING (PS&E)COMPLETED 05/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 05/15/06
TO COUNCIL FOR AWARDCOMPLETED 06/13/06
BEGIN CONSTRUCTIONCOMPLETED 07/24/06
END CONSTRUCTIONCOMPLETED 12/22/06

PROJECT NO. CIP 04-118 STREET IMPROVEMENTS – STRAND BIKEWAY LIGHT FIXTURE REPLACEMENT - MICHAEL FLAHERTY

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGN/A
DESIGN & ENGINEERING (PS&E)N/A
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 12/01/05
TO COUNCIL FOR AWARDCOMPLETED 01/10/06
BEGIN CONSTRUCTIONCOMPLETED 07/01/06
END CONSTRUCTION11/06

PROJECT NO. CIP 05-119 STREET IMPROVEMENTS – HERMOSA AVE., LONGFELLOW AVE. – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGN/A
DESIGN & ENGINEERING (PS&E)04/07
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISETBD
BID OPENINGTBD
TO COUNCIL FOR AWARD2ND QTR FY 06-07
BEGIN CONSTRUCTIONTBD
END CONSTRUCTIONTBD

PROJECT NO. CIP 05-120 STREET IMPROVEMENTS – VARIOUS LOCATIONS – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 04/04/06
DESIGN & ENGINEERING (PS&E)COMPLETED 05/05/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 05/15/06
TO COUNCIL FOR AWARDCOMPLETED 06/13/06
BEGIN CONSTRUCTIONTO BEGIN 07/24/06
END CONSTRUCTIONCOMPLETED 12/22/06

PROJECT NO. CIP 05-121 STREET IMPROVEMENTS – AVIATION BLVD. TREE PROJECT – PROJECT ENGINEER: KEN REAMEY

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 8/31/05
DESIGN & ENGINEERING (PS&E)COMPLETED 07/13/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 07/31/06
TO COUNCIL FOR AWARDCOMPLETED 08/08/06
BEGIN CONSTRUCTIONCOMPLETED 12/18/06
END CONSTRUCTION03/07

PROJECT NO. CIP 06-124 STREET IMPROVEMENTS – 16TH STREET BETWEEN PCH AND PROSPECT SIDEWALK REPAIR – PROJECT ENGINEER: KEN REAMEY

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERING07/07
DESIGN & ENGINEERING (PS&E)TBD
TO PW COMMISSION FOR REVIEWTBD
TO COUNCIL FOR APPROVAL TO ADVERTISETBD
BID OPENINGTBD
TO COUNCIL FOR AWARDTBD
BEGIN CONSTRUCTIONTBD
END CONSTRUCTIONTBD

PROJECT NO. CIP 00-413 SEWER IMPROVEMENTS – TARGET AREAS 2 THRU 4 – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
 
PRELIMINARY ENGINEERINGCOMPLETED 07/15/05
DESIGN & ENGINEERING (PS&E)COMPLETED 07/13/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENING03/07
TO COUNCIL FOR AWARD04/07
BEGIN CONSTRUCTION05/07
END CONSTRUCTION07/07

PROJECT NO. CIP 03-418 UPGRADE OF SEWER PUMP STATIONS – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
 
PRELIMINARY ENGINEERINGCOMPLETED 04/28/05
DESIGN & ENGINEERING (PS&E)COMPLETED 12/31/05
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISECOMPLETED 07/26/05
BID OPENINGCOMPLETED 04/27/06
TO COUNCIL FOR AWARDCOMPLETED 05/18/06
BEGIN CONSTRUCTIONTO BEGIN 07/05/06
END CONSTRUCTIONCOMPLETED 11/1/06

PROJECT NO. CIP 06-419 SANITARY SEWER MASTER PLAN – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
 
PRELIMINARY ENGINEERING06/07
ENGINEERING & PLAN PREPARATION09/07
TO PW COMMISSION FOR REVIEW10/07
TO COUNCIL FOR APPROVAL TO ADVERTISE11/07
BEGIN IMPLEMENTATION11/07

PROJECT NO. CIP 04-534 PARK IMPROVEMENTS – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS-REVISED
E. RODAWAY PARK
PRELIMINARY ENGINEERINGCOMPLETED 02/28/07
DESIGN & ENGINEERING (PS&E)03/07
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISETBD
BID OPENINGTBD
TO COUNCIL FOR AWARD04/07
BEGIN CONSTRUCTION04/07
END CONSTRUCTION05/07

PROJECT NO. CIP 04-535 CLARK FIELD IMPROVEMENTS – PROJECT ENGINEER: KEN REAMEY

DESCRIPTIONSTATUS
                REVISED
PRELIMINARY ENGINEERINGCOMPLETED 04/13/06
DESIGN & ENGINEERING (PS&E)COMPLETED 07/07/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 08/08/06
TO COUNCIL FOR AWARDCOMPLETED 08/08/06
BEGIN CONSTRUCTIONCOMPLETED 09/08/06
END CONSTRUCTIONCOMPLETED 02/07/07

PROJECT NO. CIP 02-612 PUBLIC WORKS YARD RENOVATION – PHASE 2 – PROJECT ENGINEER: HOMAYOUN BEHBOODI

DESCRIPTIONSTATUS
                REVISED
PRELIMINARY ENGINEERINGCOMPLETED 09/18/06
DESIGN & ENGINEERING (PS&E)05/07
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISETBD
BID OPENINGTBD
TO COUNCIL FOR AWARDTBD
BEGIN CONSTRUCTIONTBD
END CONSTRUCTIONTBD

PROJECT NO. CIP 02-626 COMMUNITY CENTER THEATER ADA UPGRADES PHASE 3 – PROJECT ENGINEER: KEN REAMEY

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 9/30/04
DESIGN & ENGINEERING (PS&E)COMPLETED 7/10/05
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 02/09/06
TO COUNCIL FOR AWARDCOMPLETED 03/28/06
BEGIN CONSTRUCTIONCOMPLETED 05/02/06
END CONSTRUCTIONCOMPLETED 01/17/07

PROJECT NO. CIP 99-631 BEACH RESTROOMS – REHABILITATION – PROJECT ENGINEER: KEN REAMEY

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERING06/07
DESIGN & ENGINEERING (PS&E)10/07
TO PW COMMISSION FOR REVIEW11/07
TO COUNCIL FOR APPROVAL TO ADVERTISETBD – PENDING FUNDINGAVAILABILITY
BID OPENINGTBD – PENDING FUNDING AVAILABILITY
TO COUNCIL FOR AWARDTBD – PENDING FUNDING AVAILABILITY
BEGIN CONSTRUCTIONTBD – PENDING FUNDING AVAILABILITY
END CONSTRUCTIONTBD – PENDING FUNDING AVAILABILITY

PROJECT NO. CIP 06-641 CLARK BUILDING REFURBISHMENT – PROJECT ENGINEER: KEN REAMEY

DESCRIPTIONSTATUS
PRELIMINARY ENGINEERINGN/A
DESIGN & ENGINEERING (PS&E)COMPLETED 10/31/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 11/09/06
TO COUNCIL FOR AWARDCOMPLETED 12/12/06
BEGIN CONSTRUCTIONCOMPLETED 01/16/07
END CONSTRUCTIONCOMPLETED 02/03/07

PROJECT NO. CIP 06-644 COMMUNITY CENTER UPGRADES – PHASE 4 – PROJECT ENGINEER: KEN REAMEY

DESCRIPTIONSTATUS
                REVISED
PRELIMINARY ENGINEERINGCOMPLETED 01/31/07
DESIGN & ENGINEERING (PS&E)03/07
TO PW COMMISSION FOR REVIEW04/07
TO COUNCIL FOR APPROVAL TO ADVERTISE05/07
BID OPENING06/07
TO COUNCIL FOR AWARD06/07
BEGIN CONSTRUCTION07/07
END CONSTRUCTION09/07

* TBD - TO BE DETERMINED