Recommendation:
It is recommended that Council receive and file this report.
Summary:
This report gives the status of capital improvement projects that are either under design or construction. Capital improvement projects not indicated in this report can be found in the department's Monthly Activity Report.
Project Status:
PROJECT NO. CIP 02-104 BAYVIEW POST-UNDERGROUNDING STREET IMPROVEMENTS – PROJECT ENGINEER: FRANK SENTENO
DESCRIPTION | STATUS |
REVISED |
PRELIMINARY ENGINEERING | COMPLETED 12/09/05 |
DESIGN & ENGINEERING (PS&E) | COMPLETED 01/12/07 |
TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD |
BID OPENING | TBD |
TO COUNCIL FOR AWARD | TBD |
BEGIN CONSTRUCTION | 3RD QTR FY 06-07 EST. |
END CONSTRUCTION | TBD |
PROJECT NO. CIP 02-106 BEACH DRIVE POST-UNDERGROUNDING STREET IMPROVEMENTS – PROJECT ENGINEER: FRANK SENTENO
DESCRIPTION | STATUS |
REVISED |
PRELIMINARY ENGINEERING | COMPLETED 03-10-05 |
DESIGN & ENGINEERING (PS&E) | COMPLETED 11/08/06 |
TO PW COMMISSION FOR REVIEW | N/A |
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
BID OPENING | N/A |
TO COUNCIL FOR AWARD | 10/24/06 ADDED TO OTHER CIP PROJECT |
BEGIN CONSTRUCTION | COMPLETED 01/08/07 |
END CONSTRUCTION | COMPLETED 1/26/07 |
PROJECT NO. CIP 05-109 CONCRETE ROAD RECONSTRUCTION – VARIOUS LOCATIONS – PROJECT ENGINEER: FRANK SENTENO
DESCRIPTION | STATUS |
|
PRELIMINARY ENGINEERING | COMPLETED 04/06 |
DESIGN & ENGINEERING (PS&E) | COMPLETED 04/06 |
TO PW COMMISSION FOR REVIEW | N/A |
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
BID OPENING | COMPLETED 05/15/06 |
TO COUNCIL FOR AWARD | COMPLETED 06/13/06 |
BEGIN CONSTRUCTION | COMPLETED 07/24/06 |
END CONSTRUCTION | COMPLETED 12/22/06 |
PROJECT NO. CIP 05-110 SLURRY/CRACK SEALING AT VARIOUS LOCATIONS – PROJECT ENGINEER: FRANK SENTENO
DESCRIPTION | STATUS |
REVISED |
PRELIMINARY ENGINEERING | COMPLETED 10/20/05 |
DESIGN & ENGINEERING (PS&E) | COMPLETED 04/12/06 |
TO PW COMMISSION FOR REVIEW | N/A |
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
BID OPENING | COMPLETED 10/12/06 |
TO COUNCIL FOR AWARD | 11/14/06 |
BEGIN CONSTRUCTION | 03/07 |
END CONSTRUCTION | 03/07 |
PROJECT NO. CIP 04-112 STREET IMPROVEMENTS – SLURRY SEAL AT VARIOUS LOCATIONS – PROJECT ENGINEER: FRANK SENTENO
DESCRIPTION | STATUS |
REVISED |
PRELIMINARY ENGINEERING | COMPLETED 03/04/05 |
DESIGN & ENGINEERING (PS&E) | COMPLETED 04/12/06 |
TO PW COMMISSION FOR REVIEW | N/A |
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
BID OPENING | COMPLETED 10/12/06 |
TO COUNCIL FOR AWARD | 11/14/06 |
BEGIN CONSTRUCTION | COMPLETED 03/26/07 |
END CONSTRUCTION | 03/07 |
PROJECT NO. CIP 04-116 STREET IMPROVEMENTS – PIER AVE., HERMOSA AVE. TO PCH – PROJECT ENGINEER: FRANK SENTENO
DESCRIPTION | STATUS |
REVISED |
PRELIMINARY ENGINEERING | TBD |
DESIGN & ENGINEERING (PS&E) | TBD |
TO PW COMMISSION FOR REVIEW | TBD |
TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD |
BID OPENING | TBD |
TO COUNCIL FOR AWARD | TBD |
BEGIN CONSTRUCTION | TBD |
END CONSTRUCTION | TBD |
PROJECT NO. CIP 04-117 STREET IMPROVEMENTS – MANHATTAN AVE. 1ST ST. TO CITY LIMITS – PROJECT ENGINEER: FRANK SENTENO
DESCRIPTION | STATUS |
REVISED |
PRELIMINARY ENGINEERING | COMPLETED 04/06 |
DESIGN & ENGINEERING (PS&E) | COMPLETED 05/06 |
TO PW COMMISSION FOR REVIEW | N/A |
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
BID OPENING | COMPLETED 05/15/06 |
TO COUNCIL FOR AWARD | COMPLETED 06/13/06 |
BEGIN CONSTRUCTION | COMPLETED 07/24/06 |
END CONSTRUCTION | COMPLETED 12/22/06 |
PROJECT NO. CIP 04-118 STREET IMPROVEMENTS – STRAND BIKEWAY LIGHT FIXTURE REPLACEMENT - MICHAEL FLAHERTY
DESCRIPTION | STATUS |
REVISED |
PRELIMINARY ENGINEERING | N/A |
DESIGN & ENGINEERING (PS&E) | N/A |
TO PW COMMISSION FOR REVIEW | N/A |
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
BID OPENING | COMPLETED 12/01/05 |
TO COUNCIL FOR AWARD | COMPLETED 01/10/06 |
BEGIN CONSTRUCTION | COMPLETED 07/01/06 |
END CONSTRUCTION | 11/06 |
PROJECT NO. CIP 05-119 STREET IMPROVEMENTS – HERMOSA AVE., LONGFELLOW AVE. – PROJECT ENGINEER: FRANK SENTENO
DESCRIPTION | STATUS |
REVISED |
PRELIMINARY ENGINEERING | N/A |
DESIGN & ENGINEERING (PS&E) | 04/07 |
TO PW COMMISSION FOR REVIEW | N/A |
TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD |
BID OPENING | TBD |
TO COUNCIL FOR AWARD | 2ND QTR FY 06-07 |
BEGIN CONSTRUCTION | TBD |
END CONSTRUCTION | TBD |
PROJECT NO. CIP 05-120 STREET IMPROVEMENTS – VARIOUS LOCATIONS – PROJECT ENGINEER: FRANK SENTENO
DESCRIPTION | STATUS |
REVISED |
PRELIMINARY ENGINEERING | COMPLETED 04/04/06 |
DESIGN & ENGINEERING (PS&E) | COMPLETED 05/05/06 |
TO PW COMMISSION FOR REVIEW | N/A |
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
BID OPENING | COMPLETED 05/15/06 |
TO COUNCIL FOR AWARD | COMPLETED 06/13/06 |
BEGIN CONSTRUCTION | TO BEGIN 07/24/06 |
END CONSTRUCTION | COMPLETED 12/22/06 |
PROJECT NO. CIP 05-121 STREET IMPROVEMENTS – AVIATION BLVD. TREE PROJECT – PROJECT ENGINEER: KEN REAMEY
DESCRIPTION | STATUS |
REVISED |
PRELIMINARY ENGINEERING | COMPLETED 8/31/05 |
DESIGN & ENGINEERING (PS&E) | COMPLETED 07/13/06 |
TO PW COMMISSION FOR REVIEW | N/A |
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
BID OPENING | COMPLETED 07/31/06 |
TO COUNCIL FOR AWARD | COMPLETED 08/08/06 |
BEGIN CONSTRUCTION | COMPLETED 12/18/06 |
END CONSTRUCTION | 03/07 |
PROJECT NO. CIP 06-124 STREET IMPROVEMENTS – 16TH STREET BETWEEN PCH AND PROSPECT SIDEWALK REPAIR – PROJECT ENGINEER: KEN REAMEY
DESCRIPTION | STATUS |
REVISED |
PRELIMINARY ENGINEERING | 07/07 |
DESIGN & ENGINEERING (PS&E) | TBD |
TO PW COMMISSION FOR REVIEW | TBD |
TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD |
BID OPENING | TBD |
TO COUNCIL FOR AWARD | TBD |
BEGIN CONSTRUCTION | TBD |
END CONSTRUCTION | TBD |
PROJECT NO. CIP 00-413 SEWER IMPROVEMENTS – TARGET AREAS 2 THRU 4 – PROJECT ENGINEER: FRANK SENTENO
DESCRIPTION | STATUS |
|
PRELIMINARY ENGINEERING | COMPLETED 07/15/05 |
DESIGN & ENGINEERING (PS&E) | COMPLETED 07/13/06 |
TO PW COMMISSION FOR REVIEW | N/A |
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
BID OPENING | 03/07 |
TO COUNCIL FOR AWARD | 04/07 |
BEGIN CONSTRUCTION | 05/07 |
END CONSTRUCTION | 07/07 |
PROJECT NO. CIP 03-418 UPGRADE OF SEWER PUMP STATIONS – PROJECT ENGINEER: FRANK SENTENO
DESCRIPTION | STATUS |
| |
PRELIMINARY ENGINEERING | COMPLETED 04/28/05 |
DESIGN & ENGINEERING (PS&E) | COMPLETED 12/31/05 |
TO PW COMMISSION FOR REVIEW | N/A |
TO COUNCIL FOR APPROVAL TO ADVERTISE | COMPLETED 07/26/05 |
BID OPENING | COMPLETED 04/27/06 |
TO COUNCIL FOR AWARD | COMPLETED 05/18/06 |
BEGIN CONSTRUCTION | TO BEGIN 07/05/06 |
END CONSTRUCTION | COMPLETED 11/1/06 |
PROJECT NO. CIP 06-419 SANITARY SEWER MASTER PLAN – PROJECT ENGINEER: FRANK SENTENO
DESCRIPTION | STATUS |
| |
PRELIMINARY ENGINEERING | 06/07 |
ENGINEERING & PLAN PREPARATION | 09/07 |
TO PW COMMISSION FOR REVIEW | 10/07 |
TO COUNCIL FOR APPROVAL TO ADVERTISE | 11/07 |
BEGIN IMPLEMENTATION | 11/07 |
PROJECT NO. CIP 04-534 PARK IMPROVEMENTS – PROJECT ENGINEER: FRANK SENTENO
DESCRIPTION | STATUS-REVISED |
E. RODAWAY PARK |
PRELIMINARY ENGINEERING | COMPLETED 02/28/07 |
DESIGN & ENGINEERING (PS&E) | 03/07 |
TO PW COMMISSION FOR REVIEW | N/A |
TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD |
BID OPENING | TBD |
TO COUNCIL FOR AWARD | 04/07 |
BEGIN CONSTRUCTION | 04/07 |
END CONSTRUCTION | 05/07 |
PROJECT NO. CIP 04-535 CLARK FIELD IMPROVEMENTS – PROJECT ENGINEER: KEN REAMEY
DESCRIPTION | STATUS |
| REVISED |
PRELIMINARY ENGINEERING | COMPLETED 04/13/06 |
DESIGN & ENGINEERING (PS&E) | COMPLETED 07/07/06 |
TO PW COMMISSION FOR REVIEW | N/A |
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
BID OPENING | COMPLETED 08/08/06 |
TO COUNCIL FOR AWARD | COMPLETED 08/08/06 |
BEGIN CONSTRUCTION | COMPLETED 09/08/06 |
END CONSTRUCTION | COMPLETED 02/07/07 |
PROJECT NO. CIP 02-612 PUBLIC WORKS YARD RENOVATION – PHASE 2 – PROJECT ENGINEER: HOMAYOUN BEHBOODI
DESCRIPTION | STATUS |
| REVISED |
PRELIMINARY ENGINEERING | COMPLETED 09/18/06 |
DESIGN & ENGINEERING (PS&E) | 05/07 |
TO PW COMMISSION FOR REVIEW | N/A |
TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD |
BID OPENING | TBD |
TO COUNCIL FOR AWARD | TBD |
BEGIN CONSTRUCTION | TBD |
END CONSTRUCTION | TBD |
PROJECT NO. CIP 02-626 COMMUNITY CENTER THEATER ADA UPGRADES PHASE 3 – PROJECT ENGINEER: KEN REAMEY
DESCRIPTION | STATUS |
REVISED |
PRELIMINARY ENGINEERING | COMPLETED 9/30/04 |
DESIGN & ENGINEERING (PS&E) | COMPLETED 7/10/05 |
TO PW COMMISSION FOR REVIEW | N/A |
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
BID OPENING | COMPLETED 02/09/06 |
TO COUNCIL FOR AWARD | COMPLETED 03/28/06 |
BEGIN CONSTRUCTION | COMPLETED 05/02/06 |
END CONSTRUCTION | COMPLETED 01/17/07 |
PROJECT NO. CIP 99-631 BEACH RESTROOMS – REHABILITATION – PROJECT ENGINEER: KEN REAMEY
DESCRIPTION | STATUS |
REVISED |
PRELIMINARY ENGINEERING | 06/07 |
DESIGN & ENGINEERING (PS&E) | 10/07 |
TO PW COMMISSION FOR REVIEW | 11/07 |
TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD – PENDING FUNDINGAVAILABILITY |
BID OPENING | TBD – PENDING FUNDING AVAILABILITY |
TO COUNCIL FOR AWARD | TBD – PENDING FUNDING AVAILABILITY |
BEGIN CONSTRUCTION | TBD – PENDING FUNDING AVAILABILITY |
END CONSTRUCTION | TBD – PENDING FUNDING AVAILABILITY |
PROJECT NO. CIP 06-641 CLARK BUILDING REFURBISHMENT – PROJECT ENGINEER: KEN REAMEY
DESCRIPTION | STATUS |
PRELIMINARY ENGINEERING | N/A |
DESIGN & ENGINEERING (PS&E) | COMPLETED 10/31/06 |
TO PW COMMISSION FOR REVIEW | N/A |
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
BID OPENING | COMPLETED 11/09/06 |
TO COUNCIL FOR AWARD | COMPLETED 12/12/06 |
BEGIN CONSTRUCTION | COMPLETED 01/16/07 |
END CONSTRUCTION | COMPLETED 02/03/07 |
PROJECT NO. CIP 06-644 COMMUNITY CENTER UPGRADES – PHASE 4 – PROJECT ENGINEER: KEN REAMEY
DESCRIPTION | STATUS |
| REVISED |
PRELIMINARY ENGINEERING | COMPLETED 01/31/07 |
DESIGN & ENGINEERING (PS&E) | 03/07 |
TO PW COMMISSION FOR REVIEW | 04/07 |
TO COUNCIL FOR APPROVAL TO ADVERTISE | 05/07 |
BID OPENING | 06/07 |
TO COUNCIL FOR AWARD | 06/07 |
BEGIN CONSTRUCTION | 07/07 |
END CONSTRUCTION | 09/07 |
* TBD - TO BE DETERMINED