Project Status Report July 2007

Recommendation:

It is recommended that Council receive and file this report.

Summary:

This report gives the status of capital improvement projects that are either under design or construction. Capital improvement projects not indicated in this report can be found in the department's Monthly Activity Report.

Project Status:

PROJECT NO. CIP 02-104 BAYVIEW POST-UNDERGROUNDING STREET IMPROVEMENTS – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 12/09/05
DESIGN & ENGINEERING (PS&E)09/06
TO COUNCIL FOR APPROVAL TO ADVERTISETBD
BID OPENINGTBD
TO COUNCIL FOR AWARDTBD
BEGIN CONSTRUCTION3RD QTR FY 06-07 EST.
END CONSTRUCTIONTBD

PROJECT NO. CIP 02-106 BEACH DRIVE POST-UNDERGROUNDING STREET IMPROVEMENTS – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 03/10/05
DESIGN & ENGINEERING (PS&E)08/06
TO COUNCIL FOR APPROVAL TO ADVERTISE08/06
BID OPENINGTBD UPON COMPLETION OF UUD
TO COUNCIL FOR AWARDTBD UPON COMPLETION OF UUD
BEGIN CONSTRUCTION2nd QTR FY 06-07 EST.
END CONSTRUCTIONTBD UPON COMPLETION OF UUD

PROJECT NO. CIP 05-109 CONCRETE ROAD RECONSTRUCTION – VARIOUS LOCATIONS – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
 
PRELIMINARY ENGINEERINGCOMPLETED 04/06
DESIGN & ENGINEERING (PS&E)COMPLETED 04/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 05/15/06
TO COUNCIL FOR AWARDCOMPLETED 06/13/06
BEGIN CONSTRUCTIONCOMPLETED 07/24/06
END CONSTRUCTION10/06

PROJECT NO. CIP 05-110 SLURRY/CRACK SEALING AT VARIOUS LOCATIONS – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 10/20/05
DESIGN & ENGINEERING (PS&E)COMPLETED 04/12/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENING09/06
TO COUNCIL FOR AWARD09/06
BEGIN CONSTRUCTION10/06
END CONSTRUCTION10/06

PROJECT NO. CIP 04-112 STREET IMPROVEMENTS – SLURRY SEAL AT VARIOUS LOCATIONS – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 03/04/05
DESIGN & ENGINEERING (PS&E)COMPLETED 04/12/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENING09/06
TO COUNCIL FOR AWARD09/06
BEGIN CONSTRUCTION10/06
END CONSTRUCTION10/06

PROJECT NO. CIP 04-116 STREET IMPROVEMENTS – PIER AVE., HERMOSA AVE. TO PCH – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERING08/06
DESIGN & ENGINEERING (PS&E)10/06
TO PW COMMISSION FOR REVIEW12/06
TO COUNCIL FOR APPROVAL TO ADVERTISE01/07
BID OPENING02/07
TO COUNCIL FOR AWARD03/07
BEGIN CONSTRUCTION04/07
END CONSTRUCTION09/07

PROJECT NO. CIP 04-117 STREET IMPROVEMENTS – MANHATTAN AVE. 1ST ST. TO CITY LIMITS – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 04/06
DESIGN & ENGINEERING (PS&E)COMPLETED 05/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 05/15/06
TO COUNCIL FOR AWARDCOMPLETED 06/13/06
BEGIN CONSTRUCTIONCOMPLETED 07/24/06
END CONSTRUCTION10/06

PROJECT NO. CIP 04-118 STREET IMPROVEMENTS – STRAND BIKEWAY LIGHT FIXTURE REPLACEMENT - MICHAEL FLAHERTY

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGN/A
DESIGN & ENGINEERING (PS&E)N/A
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 12/01/05
TO COUNCIL FOR AWARDCOMPLETED 01/10/06
BEGIN CONSTRUCTIONCOMPLETED 07/01/06
END CONSTRUCTION09/06

PROJECT NO. CIP 05-119 STREET IMPROVEMENTS – HERMOSA AVE., LONGFELLOW AVE. – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
 
PRELIMINARY ENGINEERINGTBD
DESIGN & ENGINEERING (PS&E)TBD
TO PW COMMISSION FOR REVIEWTBD
TO COUNCIL FOR APPROVAL TO ADVERTISETBD
BID OPENINGTBD
TO COUNCIL FOR AWARD2nd QTR FY 06-07
BEGIN CONSTRUCTIONTBD
END CONSTRUCTIONTBD

PROJECT NO. CIP 05-120 STREET IMPROVEMENTS – VARIOUS LOCATIONS – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 04/06
DESIGN & ENGINEERING (PS&E)05/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 05/15/06
TO COUNCIL FOR AWARDCOMPLETED 06/13/06
BEGIN CONSTRUCTIONTO BEGIN 07/24/06
END CONSTRUCTION10/06

PROJECT NO. CIP 05-121 STREET IMPROVEMENTS – AVIATION BLVD. TREE PROJECT – PROJECT ENGINEER: KEN REAMEY

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 08/31/05
DESIGN & ENGINEERING (PS&E)COMPLETED 07/13/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 07/31/06
TO COUNCIL FOR AWARDCOMPLETED 08/08/06
BEGIN CONSTRUCTION09/06
END CONSTRUCTION10/06

PROJECT NO. CIP 06-124 STREET IMPROVEMENTS – 16TH STREET BETWEEN PCH AND PROSPECT SIDEWALK REPAIR – PROJECT ENGINEER: KEN REAMEY

DESCRIPTIONSTATUS
 
PRELIMINARY ENGINEERING01/07
DESIGN & ENGINEERING (PS&E)02/07
TO PW COMMISSION FOR REVIEWTBD
TO COUNCIL FOR APPROVAL TO ADVERTISETBD
BID OPENINGTBD
TO COUNCIL FOR AWARDTBD
BEGIN CONSTRUCTIONTBD
END CONSTRUCTIONTBD

PROJECT NO. CIP 00-413 SEWER IMPROVEMENTS – TARGET AREAS 2 THRU 4 – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
 
PRELIMINARY ENGINEERINGCOMPLETED 07/15/05
DESIGN & ENGINEERING (PS&E)COMPLETED 07/13/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISE10/06
BID OPENING11/06
TO COUNCIL FOR AWARD12/06
BEGIN CONSTRUCTION01/07
END CONSTRUCTION03/07

PROJECT NO. CIP 03-418 UPGRADE OF SEWER PUMP STATIONS – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
 
PRELIMINARY ENGINEERINGCOMPLETED 04/28/05
DESIGN & ENGINEERING (PS&E)COMPLETED 12/31/05
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISECOMPLETED 07/26/05
BID OPENINGCOMPLETED 04/27/06
TO COUNCIL FOR AWARDCOMPLETED 05/18/06
BEGIN CONSTRUCTIONTO BEGIN 07/05/06
END CONSTRUCTION09/06

PROJECT NO. CIP 06-419 SANITARY SEWER MASTER PLAN – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS
 
PRELIMINARY ENGINEERING12/06
DESIGN & ENGINEERING (PS&E)12/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISE12/06
BID OPENING12/06
TO COUNCIL FOR AWARD12/06
BEGIN CONSTRUCTION12/06
END CONSTRUCTION12/06

PROJECT NO. CIP 04-534 PARK IMPROVEMENTS – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTIONSTATUS - REVISED
E. RODAWAY PARK
PRELIMINARY ENGINEERING09/06
DESIGN & ENGINEERING (PS&E)10/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISE11/06
BID OPENING11/06
TO COUNCIL FOR AWARD12/06
BEGIN CONSTRUCTION01/07
END CONSTRUCTION02/07

PROJECT NO. CIP 04-535 CLARK FIELD IMPROVEMENTS – PROJECT ENGINEER: KEN REAMEY

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 04/13/06
DESIGN & ENGINEERING (PS&E)07/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENING08/06
TO COUNCIL FOR AWARD08/06
BEGIN CONSTRUCTION09/06
END CONSTRUCTION11/06

PROJECT NO. CIP 02-612 PUBLIC WORKS YARD RENOVATION – PHASE 2 – PROJECT ENGINEER: HOMAYOUN BEHBOODI

DESCRIPTIONSTATUS
               
PRELIMINARY ENGINEERINGCOMPLETED 11/01/05
DESIGN & ENGINEERING (PS&E)COMPLETED 11/08/05
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISE02/07
BID OPENING03/07
TO COUNCIL FOR AWARD03/07
BEGIN CONSTRUCTION04/07
END CONSTRUCTIONTBD

PROJECT NO. CIP 02-626 COMMUNITY CENTER THEATER ADA UPGRADES PHASE 3 – PROJECT ENGINEER: KEN REAMEY

DESCRIPTIONSTATUS
               REVISED
PRELIMINARY ENGINEERINGCOMPLETED 09/30/04
DESIGN & ENGINEERING (PS&E)COMPLETED 07/10/05
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL OF DESIGN & SPECSN/A
BID OPENINGCOMPLETED 02/09/06
TO COUNCIL FOR AWARDCOMPLETED 03/28/06
BEGIN CONSTRUCTIONCOMPLETED 05/02/06
END CONSTRUCTION10/06

PROJECT NO. CIP 99-631 BEACH RESTROOMS – REHABILITATION – PROJECT ENGINEER: KEN REAMEY

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 03/31/06
DESIGN & ENGINEERING (PS&E)10/06
TO PW COMMISSION FOR REVIEW10/06
TO COUNCIL FOR APPROVAL TO ADVERTISETBD – PENDING FUNDINGAVAILABILITY
BID OPENINGTBD – PENDING FUNDING AVAILABILITY
TO COUNCIL FOR AWARDTBD – PENDING FUNDING AVAILABILITY
BEGIN CONSTRUCTIONTBD – PENDING FUNDING AVAILABILITY
END CONSTRUCTIONTBD – PENDING FUNDING AVAILABILITY

PROJECT NO. CIP 06-641 CLARK BUILDING REFURBISHMENT – PROJECT ENGINEER: KEN REAMEY

DESCRIPTIONSTATUS
 
PRELIMINARY ENGINEERINGN/A
DESIGN & ENGINEERING (PS&E)10/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENING11/06
TO COUNCIL FOR AWARD11/06
BEGIN CONSTRUCTION12/06
END CONSTRUCTION01/07

PROJECT NO. CIP 06-644 COMMUNITY CENTER UPGRADES – PHASE 4 – PROJECT ENGINEER: KEN REAMEY

DESCRIPTIONSTATUS
                
PRELIMINARY ENGINEERING01/07
DESIGN & ENGINEERING (PS&E)02/07
TO PW COMMISSION FOR REVIEW04/07
TO COUNCIL FOR APPROVAL TO ADVERTISE05/07
BID OPENING06/07
TO COUNCIL FOR AWARD06/07
BEGIN CONSTRUCTION07/07
END CONSTRUCTION09/07

* TBD - TO BE DETERMINED