Project Status Report January 2009

Recommendation:

It is recommended that Council receive and file this report.

Summary:

This report gives the status of capital improvement projects that are either under design or construction. Capital improvement projects not indicated in this report can be found in the department's Monthly Activity Report.

Project Status:

PROJECT NO. CIP 02-104 BAYVIEW POST/UNDERGROUNDING STREET IMPROVEMENTS – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTION STATUS
REVISED
PRELIMINARY ENGINEERING COMPLETED 12/09/05
DESIGN & ENGINEERING (PS&E) COMPLETED 01/12/07
TO COUNCIL FOR APPROVAL TO ADVERTISE TBD
BID OPENING TBD
TO COUNCIL FOR AWARD TBD
BEGIN CONSTRUCTION TBD
END CONSTRUCTION TBD

PROJECT NO. CIP 04-116 STREET IMPROVEMENTS – PIER AVE., HERMOSA AVE. TO PCH – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTION STATUS
REVISED
PRELIMINARY ENGINEERING COMPLETED 10/28/08
DESIGN & ENGINEERING (PS&E) 04/09
TO PW COMMISSION FOR REVIEW 05/09
TO COUNCIL FOR APPROVAL TO ADVERTISE 06/09
BID OPENING 07/09
TO COUNCIL FOR AWARD 07/09
BEGIN CONSTRUCTION 07/09
END CONSTRUCTION TBD

PROJECT NO. CIP 05-119 STREET IMPROVEMENTS – HERMOSA AVE., LONGFELLOW AVE. – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTION STATUS
REVISED
PRELIMINARY ENGINEERING COMPLETED 05/24/07
DESIGN & ENGINEERING (PS&E) COMPLETED 05/28/08
TO PW COMMISSION FOR REVIEW N/A
TO COUNCIL FOR APPROVAL TO ADVERTISE N/A
BID OPENING COMPLETED 09/11/08
TO COUNCIL FOR AWARD COMPLETED 09/23/08
BEGIN CONSTRUCTION COMPLETED 10/27/08
END CONSTRUCTION TBD

PROJECT NO. CIP 08-127 STREET IMPROVEMENTS, PROJECT ENGINEER: FRANK SENTENO

DESCRIPTION STATUS
REVISED

PRELIMINARY ENGINEERING COMPLETED 09/18/08
DESIGN & ENGINEERING (PS&E) 03/09
TO PW COMMISSION FOR REVIEW N/A
TO COUNCIL FOR APPROVAL TO ADVERTISE COMPLETED 09/23/08
BID OPENING TBD
TO COUNCIL FOR AWARD TBD
BEGIN CONSTRUCTION TBD
END CONSTRUCTION TBD

PROJECT NO. CIP 07-132 STREET IMPROVEMENTS – SLURRY SEAL AT VARIOUS LOCATIONS – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTION STATUS
REVISED
PRELIMINARY ENGINEERING COMPLETED 02/07/08
DESIGN & ENGINEERING (PS&E) COMPLETED 04/23/08
TO PW COMMISSION FOR REVIEW N/A
TO COUNCIL FOR APPROVAL TO ADVERTISE N/A
BID OPENING COMPLETED 05/05/08
TO COUNCIL FOR AWARD COMPLETED 05/27/08
BEGIN CONSTRUCTION COMPLETED 06/09/08
END CONSTRUCTION

COMPLETED 08/29/08

PROJECT NO. CIP 07-420 STORM WATER TREATMENT – INFILTRATION TRENCH – PROJECT ENGINEER: HOMAYOUN BEHBOODI

DESCRIPTION STATUS
REVISED
PRELIMINARY ENGINEERING COMPLETED 07/02/07
DESIGN & ENGINEERING (PS&E) COMPLETED 08/31/07
TO PW COMMISSION FOR REVIEW N/A
TO COUNCIL FOR GRANT AGRMT. AUTHORIZATION COMPLETED 09/25/07
BID OPENING TBD
TO COUNCIL FOR AWARD TBD
BEGIN CONSTRUCTION TBD
END CONSTRUCTION TBD

PROJECT NO. CIP 07-422 SEWER MASTER PLAN – PROJECT ENGINEER: HOMAYOUN BEHBOODI

DESCRIPTION STATUS
REVISED
PRELIMINARY ENGINEERING COMPLETED 07/02/07
DESIGN & ENGINEERING (PS&E) COMPLETED 08/02/07
TO PW COMMISSION FOR REVIEW N/A
TO COUNCIL FOR APPROVAL TO ADVERTISE N/A
BID OPENING N/A
TO COUNCIL FOR AWARD/CONSULTANT SELECTED COMPLETED 09/11/07
BEGIN CONSTRUCTION/BEGIN WORK COMPLETED 09/12/07
END CONSTRUCTION 02/09

PROJECT NO. CIP 08-425 SEWER IMPROVEMENTS, VARIOUS LOCATIONS – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTION STATUS

PRELIMINARY ENGINEERING TBD
DESIGN & ENGINEERING (PS&E) TBD
TO PW COMMISSION FOR REVIEW TBD
TO COUNCIL FOR APPROVAL TO ADVERTISE TBD
BID OPENING TBD
TO COUNCIL FOR AWARD TBD
BEGIN CONSTRUCTION TBD
END CONSTRUCTION TBD

PROJECT NO. CIP 02-612 PUBLIC WORKS YARD RENOVATION – PHASE 2 – PROJECT ENGINEER: KEN REAMEY

DESCRIPTION STATUS
REVISED
PRELIMINARY ENGINEERING COMPLETED 09/18/06
DESIGN & ENGINEERING (PS&E) 03/09
TO PW COMMISSION FOR REVIEW N/A
TO COUNCIL FOR APPROVAL TO ADVERTISE 02/09
BID OPENING 03/09
TO COUNCIL FOR AWARD 03/09
BEGIN CONSTRUCTION 04/09
END CONSTRUCTION 10/09

PROJECT NO. CIP 99-631 BEACH RESTROOMS – REHABILITATION – PROJECT ENGINEER: KEN REAMEY

DESCRIPTION STATUS
REVISED
PRELIMINARY ENGINEERING COMPLETED 03/11/08
DESIGN & ENGINEERING (PS&E) 03/09
TO PW COMMISSION FOR REVIEW COMPLETED 05/21/08
TO COUNCIL FOR APPROVAL TO ADVERTISE 03/09
BID OPENING 04/09
TO COUNCIL FOR AWARD 05/09
BEGIN CONSTRUCTION 06/09
END CONSTRUCTION 12/09

PROJECT NO. CIP 06-640 FIRE STATION RENOVATION, HVAC – PROJECT ENGINEER: KEN REAMEY

DESCRIPTION STATUS
REVISED
PRELIMINARY ENGINEERING COMPLETED 07/12/07
DESIGN & ENGINEERING (PS&E) COMPLETED 07/12/07
TO PW COMMISSION FOR REVIEW N/A
TO COUNCIL FOR APPROVAL TO ADVERTISE N/A
BID OPENING N/A
TO COUNCIL FOR AWARD COMPLETED 08/14/07
BEGIN CONSTRUCTION COMPLETED 09/15/08
END CONSTRUCTION 03/09

PROJECT NO. CIP 07-641 CLARK BULDING REFURBISHMENTS – PROJECT ENGINEER: KEN REAMEY

DESCRIPTION STATUS
REVISED
PRELIMINARY ENGINEERING COMPLETED 04/09/08
DESIGN & ENGINEERING (PS&E) COMPLETED 08/01/08
TO PW COMMISSION FOR REVIEW N/A
TO COUNCIL FOR APPROVAL TO ADVERTISE N/A
BID OPENING COMPLETED 10/02/08
TO COUNCIL FOR AWARD COMPLETED 10/14/08
BEGIN CONSTRUCTION COMPLETED 11/03/08
END CONSTRUCTION 02/09

PROJECT NO. CIP 06-644 COMMUNITY CENTER UPGRADES – PHASE 4 – PROJECT ENGINEER: KEN REAMEY

DESCRIPTION STATUS
REVISED
PRELIMINARY ENGINEERING COMPLETED 01/31/07
DESIGN & ENGINEERING (PS&E) COMPLETED 03/03/08
TO PW COMMISSION FOR REVIEW N/A
TO COUNCIL FOR APPROVAL TO ADVERTISE N/A
BID OPENING COMPLETED 11/25/08
TO COUNCIL FOR AWARD COMPLETED 12/09/08
BEGIN CONSTRUCTION 02/09
END CONSTRUCTION 05/09

PROJECT NO. CIP 07-647 FIRE DEPARTMENT, BARD BUILDING IMPROVEMENTS – PROJECT ENGINEER: KEN REAMEY

DESCRIPTION STATUS
PRELIMINARY ENGINEERING TBD
DESIGN & ENGINEERING (PS&E) TBD
TO PW COMMISSION FOR REVIEW TBD
TO COUNCIL FOR APPROVAL TO ADVERTISE TBD
BID OPENING TBD
TO COUNCIL FOR AWARD TBD
BEGIN CONSTRUCTION TBD
END CONSTRUCTION TBD

PROJECT NO. CIP 07-649 COMMUNITY CENTER NORTH WING GENERAL IMPROEMENTS – PROJECT ENGINEER: KEN REAMEY

DESCRIPTION STATUS
PRELIMINARY ENGINEERING COMPLETED 03/31/08
DESIGN & ENGINEERING (PS&E) COMPLETED 01/15/09
TO PW COMMISSION FOR REVIEW N/A
TO COUNCIL FOR APPROVAL TO ADVERTISE N/A
BID OPENING 02/09
TO COUNCIL FOR AWARD 02/09
BEGIN CONSTRUCTION 03/09
END CONSTRUCTION 08/09

PROJECT NO. CIP 07-650 SOLAR COLLECTORS FOR PUBLIC BUILDINGS – PROJECT ENGINEER: KEN REAMEY

DESCRIPTION STATUS
PRELIMINARY ENGINEERING TBD
DESIGN & ENGINEERING (PS&E) TBD
TO PW COMMISSION FOR REVIEW TBD
TO COUNCIL FOR APPROVAL TO ADVERTISE TBD
BID OPENING TBD
TO COUNCIL FOR AWARD TBD
BEGIN CONSTRUCTION TBD
END CONSTRUCTION TBD

PROJECT NO. CIP 07-651 LOT A TRASH ENCLOSURE – PROJECT ENGINEER: KEN REAMEY

DESCRIPTION STATUS
PRELIMINARY ENGINEERING COMPLETED 12/13/07
DESIGN & ENGINEERING (PS&E)

TBD

TO PW COMMISSION FOR REVIEW N/A
TO COUNCIL FOR APPROVAL TO ADVERTISE N/A
BID OPENING TBD
TO COUNCIL FOR AWARD TBD
BEGIN CONSTRUCTION TBD
END CONSTRUCTION TBD

PROJECT NO. CIP 07-652 CIVIC CENTER MASTER PLAN – PROJECT ENGINEER: RICK MORGAN

DESCRIPTION STATUS
PRELIMINARY ENGINEERING TBD
DESIGN & ENGINEERING (PS&E) TBD
TO PW COMMISSION FOR REVIEW TBD
TO COUNCIL FOR APPROVAL TO ADVERTISE TBD
BID OPENING TBD
TO COUNCIL FOR AWARD TBD
BEGIN CONSTRUCTION TBD
END CONSTRUCTION TBD

PROJECT NO. CIP 08-653 SENIOR ACTIVITY CENTER – PROJECT ENGINEER: KEN REAMEY

DESCRIPTION STATUS
PRELIMINARY ENGINEERING COMPLETED 05/01/08
DESIGN & ENGINEERING (PS&E) 01/09
TO PW COMMISSION FOR REVIEW N/A
TO COUNCIL FOR APPROVAL TO ADVERTISE N/A
BID OPENING 02/09
TO COUNCIL FOR AWARD 02/09
BEGIN CONSTRUCTION 03/09
END CONSTRUCTION 06/09

PROJECT NO. CIP 08-654 COMMUNITY CENTER ELECTRICAL UPGRADES – PROJECT ENGINEER: KEN REAMEY

DESCRIPTION STATUS
PRELIMINARY ENGINEERING N/A
DESIGN & ENGINEERING (PS&E) COMPLETED 10/30/08
TO PW COMMISSION FOR REVIEW N/A
TO COUNCIL FOR APPROVAL TO ADVERTISE N/A
BID OPENING COMPLETED 11/20/08
TO COUNCIL FOR AWARD COMPLETED 12/09/08
BEGIN CONSTRUCTION 02/09
END CONSTRUCTION 05/09

* TBD - TO BE DETERMINED