Project Status:
PROJECT NO. CIP 04-116 STREET IMPROVEMENTS – PIER AVE., HERMOSA AVE. TO PCH – PROJECT ENGINEER: FRANK SENTENO
DESCRIPTION | STATUS | COMMENTS |
| REVISED | |
PRELIMINARY ENGINEERING | COMPLETED 10/28/08 | |
DESIGN & ENGINEERING (PS&E) | COMPLETED 10/21/09 | |
TO PW COMMISSION FOR REVIEW | N/A | |
TO COUNCIL FOR APPROVAL TO ADVERTISE | COMPLETED
10/13/09 | |
BID OPENING | COMPLETED 11/19/09 | |
TO COUNCIL FOR AWARD | COMPLETED 12/08/09 | |
BEGIN CONSTRUCTION | COMPLETED 01/11/10 | |
END CONSTRUCTION | 08/10 | |
PROJECT NO. CIP 08-127 STREET IMPROVEMENTS, PROJECT ENGINEER: FRANK SENTENO
DESCRIPTION | STATUS | COMMENTS |
| REVISED | |
PRELIMINARY ENGINEERING | COMPLETED 09/18/08 | |
DESIGN & ENGINEERING (PS&E) | 08/10 | |
TO PW COMMISSION FOR REVIEW | N/A | |
TO COUNCIL FOR APPROVAL TO ADVERTISE | COMPLETED 09/23/08 | |
BID OPENING | TBD | DELAYED DUE TO PRIORITY
FUNDING OF CITY’S TWO ARRA 2009 FEDERAL AID PROJECTS’ REQUIREMENTS (CIP 09-129
& CIP 09-135) |
TO COUNCIL FOR AWARD | TBD | |
BEGIN CONSTRUCTION | TBD | |
END CONSTRUCTION | TBD | |
PROJECT NO. CIP 09-129 PIER AVE. STREET IMPROVEMENTS, PROJECT ENGINEER:
FRANK SENTENO
DESCRIPTION | STATUS | COMMENTS |
PRELIMINARY ENGINEERING | COMPLETED 04/14/09 | |
DESIGN & ENGINEERING (PS&E) | COMPLETED 07/27/09 | |
TO PW COMMISSION FOR REVIEW | N/A | |
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
CALTRANS ISSUED AUTHORIZATION TO PROCEED WITH CON- |
BID OPENING | COMPLETED 12/10/09 | STRUCTION 11/3/09 |
TO COUNCIL FOR AWARD | 01/12/10 | |
BEGIN CONSTRUCTION | COMPLETED 04/5/10 | |
END CONSTRUCTION | 06/10 | |
PROJECT NO. CIP 09-135 8TH STREET IMPROVEMENT PROJECT, PROJECT ENGINEER:
FRANK SENTENO
DESCRIPTION | STATUS | COMMENTS |
|
REVISED | |
PRELIMINARY ENGINEERING | COMPLETED 04/14/09 | |
DESIGN & ENGINEERING (PS&E) | COMPLETED 07/27/09 | |
TO PW COMMISSION FOR REVIEW | N/A | |
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
CALTRANS ISSUED AUTHORIZATION TO PROCEED WITH CON- |
BID OPENING | COMPLETED 12/10/09 | STRUCTION 11/3/09 |
TO COUNCIL FOR AWARD | COMPLETED 01/12/10 | |
BEGIN CONSTRUCTION | COMPLETED 04/5/10 | |
END CONSTRUCTION | 06/10 | |
PROJECT NO. CIP 07-420 PIER AVE. STORM DRAIN – INFILTRATION TRENCH – PROJECT ENGINEER: HOMAYOUN BEHBOODI
DESCRIPTION | STATUS | COMMENTS |
| REVISED | |
PRELIMINARY ENGINEERING | COMPLETED 07/02/07 | |
DESIGN & ENGINEERING (PS&E) | COMPLETED 08/31/07 | |
TO COUNCIL | COMPLETED 09/25/07 | FOR GRANT AGRMT. AUTHORIZATION |
BID OPENING | COMPLETED 08/27/09 | |
TO COUNCIL FOR AWARD | COMPLETED 09/22/09 |
BEGIN CONSTRUCTION | COMPLETED 10/26/09 | |
END CONSTRUCTION | COMPLETED 04/22/10 | |
PROJECT NO. CIP 02-612 PUBLIC WORKS YARD RENOVATION – PHASE 2 – PROJECT ENGINEER: KEN REAMEY
DESCRIPTION | STATUS | COMMENTS |
| REVISED | |
PRELIMINARY ENGINEERING | COMPLETED 09/18/06 |
DESIGN & ENGINEERING (PS&E) | 07/10 | |
TO PW COMMISSION FOR REVIEW | N/A | |
ADVERTISE | 08/10 | |
BID OPENING | 09/10 | |
TO COUNCIL FOR AWARD | 09/10 | |
BEGIN CONSTRUCTION | 10/10 | |
END CONSTRUCTION | 04/11 | |
PROJECT NO. CIP 99-631 BEACH RESTROOMS AT 2ND, 14TH, & 22ND STREETS – REHABILITATION – PROJECT ENGINEER: KEN REAMEY
DESCRIPTION | STATUS | COMMENTS |
| REVISED | |
PRELIMINARY ENGINEERING | COMPLETED 03/11/08 | |
DESIGN & ENGINEERING (PS&E) | 05/10 |
COASTAL COMMISSION & ENVIRONMENTAL |
PLANNING COMMISSION APPROVAL | COMPLETED 06/16/09 | |
TO PW COMMISSION FOR REVIEW | COMPLETED 05/21/08 | |
COASTAL COMMISSION APPROVAL | 6/10 | PRELIMINARY
APPVL REC’D 1/14/10, FINAL APPVL PENDING |
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
|
BID OPENING | 07/10 | |
TO COUNCIL FOR AWARD | 08/10 | |
BEGIN CONSTRUCTION | 09/10 | |
END CONSTRUCTION | 03/11 | |
PROJECT NO. CIP 07-650 SOLAR COLLECTORS FOR PUBLIC BUILDINGS – PROJECT ENGINEER: KEN REAMEY
DESCRIPTION | STATUS | COMMENTS |
| | |
PRELIMINARY ENGINEERING | TBD | |
DESIGN & ENGINEERING (PS&E) | TBD | |
TO PW COMMISSION FOR REVIEW | TBD | |
TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD | |
BID OPENING | TBD | |
TO COUNCIL FOR AWARD | TBD | |
BEGIN CONSTRUCTION | TBD | |
END CONSTRUCTION | TBD | |
PROJECT NO. CIP 07-652 CIVIC CENTER MASTER PLAN – PROJECT ENGINEER: RICK MORGAN
DESCRIPTION | STATUS | COMMENTS |
| | |
PRELIMINARY ENGINEERING | TBD | |
DESIGN & ENGINEERING (PS&E) | TBD | |
TO PW COMMISSION FOR REVIEW | TBD | |
TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD | |
BID OPENING | TBD | |
TO COUNCIL FOR AWARD | TBD | |
BEGIN CONSTRUCTION | TBD | |
END CONSTRUCTION | TBD | |
PROJECT NO. CIP 09-659 PARKING STRUCTURE & PIER REPAIRS – PROJECT ENGINEER: KEN REAMEY
DESCRIPTION | STATUS | COMMENTS |
| | |
PRELIMINARY ENGINEERING | COMPLETED 01/27/10 |
PIER ASSESSMENT RECEIVED |
DESIGN & ENGINEERING (PS&E) | 04/15/10 | PIER
REPAIRS |
TO PW COMMISSION FOR REVIEW | N/A | |
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A | |
BID OPENING | 05/10 | PIER REPAIRS |
TO COUNCIL FOR AWARD | 05/10 | PIER REPAIRS |
BEGIN CONSTRUCTION | 06/10 | PIER REPAIRS |
END CONSTRUCTION | 07/10 | PIER REPAIRS |
PROJECT NO. CIP 09-660 FIRE STATION SEISMIC UPGRADE – PROJECT ENGINEER: KEN REAMEY
DESCRIPTION | STATUS | COMMENTS |
| | |
PRELIMINARY ENGINEERING | TBD | |
DESIGN & ENGINEERING (PS&E) | TBD | |
TO PW COMMISSION FOR REVIEW | TBD | |
TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD | |
BID OPENING | TBD | |
TO COUNCIL FOR AWARD | TBD | |
BEGIN CONSTRUCTION | TBD | |
END CONSTRUCTION | TBD | |