Project Status Report August 2010

Recommendation:

It is recommended that Council receive and file this report.

Summary:

This report gives the status of capital improvement projects that are either under design or construction. Capital improvement projects not indicated in this report can be found in the department's Monthly Activity Report.

Project Status:

PROJECT NO. CIP 04-116 STREET IMPROVEMENTS – PIER AVE., HERMOSA AVE. TO PCH – PROJECT ENGINEER: FRANK SENTENO

DESCRIPTION STATUS COMMENTS
REVISED
PRELIMINARY ENGINEERING COMPLETED 10/28/08
DESIGN & ENGINEERING (PS&E) COMPLETED 10/21/09
TO PW COMMISSION FOR REVIEW N/A
TO COUNCIL FOR APPROVAL TO ADVERTISE COMPLETED 10/13/09
BID OPENING COMPLETED 11/19/09
TO COUNCIL FOR AWARD COMPLETED 12/08/09
BEGIN CONSTRUCTION COMPLETED 01/11/10
END CONSTRUCTION 10/10

PROJECT NO. CIP 08-127 STREET IMPROVEMENTS, PROJECT ENGINEER: FRANK SENTENO

DESCRIPTION STATUS COMMENTS
REVISED
PRELIMINARY ENGINEERING COMPLETED 09/18/08
DESIGN & ENGINEERING (PS&E) 08/10
TO PW COMMISSION FOR REVIEW N/A
TO COUNCIL FOR APPROVAL TO ADVERTISE COMPLETED 09/23/08
BID OPENING TBD DELAYED DUE TO PRIORITY FUNDING OF CITY’S TWO ARRA 2009 FEDERAL AID PROJECTS’ REQUIREMENTS (CIP 09-129 & CIP 09-135)
TO COUNCIL FOR AWARD TBD
BEGIN CONSTRUCTION TBD
END CONSTRUCTION TBD

PROJECT NO. CIP 09-129 PIER AVE. STREET IMPROVEMENTS, PROJECT ENGINEER: FRANK SENTENO

DESCRIPTION STATUS COMMENTS
PRELIMINARY ENGINEERING COMPLETED 04/14/09
DESIGN & ENGINEERING (PS&E) COMPLETED 07/27/09
TO PW COMMISSION FOR REVIEW N/A
TO COUNCIL FOR APPROVAL TO ADVERTISE N/A CALTRANS ISSUED AUTHORIZATION TO PROCEED WITH CON-
BID OPENING COMPLETED 12/10/09 STRUCTION 11/3/09
TO COUNCIL FOR AWARD 01/12/10  
BEGIN CONSTRUCTION COMPLETED 04/05/10  
END CONSTRUCTION COMPLETION 07/27/10  

PROJECT NO. CIP 09-135 8TH STREET IMPROVEMENT PROJECT, PROJECT ENGINEER: FRANK SENTENO

DESCRIPTION STATUS COMMENTS
  REVISED  
PRELIMINARY ENGINEERING COMPLETED 04/14/09
DESIGN & ENGINEERING (PS&E) COMPLETED 07/27/09
TO PW COMMISSION FOR REVIEW N/A
TO COUNCIL FOR APPROVAL TO ADVERTISE N/A CALTRANS ISSUED AUTHORIZATION TO PROCEED WITH CON-
BID OPENING COMPLETED 12/10/09 STRUCTION 11/3/09
TO COUNCIL FOR AWARD COMPLETED 01/12/10  
BEGIN CONSTRUCTION COMPLETED 04/05/10  
END CONSTRUCTION COMPLETED 07/23/10  

PROJECT NO. CIP 02-612 PUBLIC WORKS YARD RENOVATION – PHASE 2 – PROJECT ENGINEER: KEN REAMEY

DESCRIPTION STATUS COMMENTS
REVISED
PRELIMINARY ENGINEERING COMPLETED 09/18/06
DESIGN & ENGINEERING (PS&E) 10/10
TO PW COMMISSION FOR REVIEW N/A
ADVERTISE 11/10
BID OPENING 12/10
TO COUNCIL FOR AWARD 12/10
BEGIN CONSTRUCTION 01/11
END CONSTRUCTION 07/11

PROJECT NO. CIP 99-631 BEACH RESTROOMS AT 2ND, 14TH, & 22ND STREETS – REHABILITATION – PROJECT ENGINEER: KEN REAMEY

DESCRIPTION STATUS COMMENTS
REVISED
PRELIMINARY ENGINEERING COMPLETED 03/11/08
DESIGN & ENGINEERING (PS&E) 08/12/10 COASTAL COMMISSION & ENVIRONMENTAL
PLANNING COMMISSION APPROVAL COMPLETED 06/16/09
TO PW COMMISSION FOR REVIEW COMPLETED 05/21/08
COASTAL COMMISSION APPROVAL COMPLETED 06/11/10 PRELIMINARY APPVL REC’D 1/14/10, FINAL APPVL PENDING
TO COUNCIL FOR APPROVAL TO ADVERTISE N/A  
BID OPENING 09/10
TO COUNCIL FOR AWARD 09/10
BEGIN CONSTRUCTION 10/10
END CONSTRUCTION 04/11

PROJECT NO. CIP 09-659 PARKING STRUCTURE & PIER REPAIRS – PROJECT ENGINEER: KEN REAMEY

DESCRIPTION STATUS COMMENTS
PRELIMINARY ENGINEERING COMPLETED 01/27/10 PIER ASSESSMENT RECEIVED
DESIGN & ENGINEERING (PS&E) 04/15/10 PIER REPAIRS
TO PW COMMISSION FOR REVIEW N/A
TO COUNCIL FOR APPROVAL TO ADVERTISE N/A
BID OPENING COMPLETED 05/11/10 PIER REPAIRS
TO COUNCIL FOR AWARD COMPLETED 06/08/10 PIER REPAIRS
BEGIN CONSTRUCTION 07/19/10 PIER REPAIRS
END CONSTRUCTION 07/26/10 PIER REPAIRS

* TBD - TO BE DETERMINED