Recommendation:
It is recommended that Council receive and file this report.
Summary:
This report gives the status of capital improvement projects that are either under design or construction. Capital improvement projects not indicated in this report can be found in the department's Monthly Activity Report.
Project Status:
PROJECT NO. CIP 04-116 STREET IMPROVEMENTS – PIER AVE., HERMOSA AVE. TO PCH – PROJECT ENGINEER: FRANK SENTENO
DESCRIPTION | STATUS | COMMENTS |
| REVISED | |
PRELIMINARY ENGINEERING | COMPLETED 10/28/08 | |
DESIGN & ENGINEERING (PS&E) | COMPLETED 10/21/09 | |
TO PW COMMISSION FOR REVIEW | N/A | |
TO COUNCIL FOR APPROVAL TO ADVERTISE | COMPLETED
10/13/09 | |
BID OPENING | COMPLETED 11/19/09 | |
TO COUNCIL FOR AWARD | COMPLETED 12/08/09 | |
BEGIN CONSTRUCTION | COMPLETED 01/11/10 | |
END CONSTRUCTION | 11/10/10 | |
PROJECT NO. CIP 08-127 STREET IMPROVEMENTS, PROJECT ENGINEER: FRANK SENTENO
DESCRIPTION | STATUS | COMMENTS |
| REVISED | |
PRELIMINARY ENGINEERING | COMPLETED 09/18/08 | |
DESIGN & ENGINEERING (PS&E) | 12/10 | |
TO PW COMMISSION FOR REVIEW | N/A | |
TO COUNCIL FOR APPROVAL TO ADVERTISE | COMPLETED 09/23/08 | |
BID OPENING | 01/11 | |
TO COUNCIL FOR AWARD | 01/11 | |
BEGIN CONSTRUCTION | 02/11 | |
END CONSTRUCTION | 04/10 | |
PROJECT NO. CIP 09-129 PIER AVE. STREET IMPROVEMENTS, PROJECT ENGINEER:
FRANK SENTENO
DESCRIPTION | STATUS | COMMENTS |
PRELIMINARY ENGINEERING | COMPLETED 04/14/09 | |
DESIGN & ENGINEERING (PS&E) | COMPLETED 07/27/09 | |
TO PW COMMISSION FOR REVIEW | N/A | |
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
CALTRANS ISSUED AUTHORIZATION TO PROCEED WITH CON- |
BID OPENING | COMPLETED 12/10/09 | STRUCTION 11/3/09 |
TO COUNCIL FOR AWARD | COMPLETED 01/12/10 | |
BEGIN CONSTRUCTION | COMPLETED 04/05/10 | |
END CONSTRUCTION | 07/27/10 | |
PROJECT NO. CIP 09-135 8TH STREET IMPROVEMENT PROJECT, PROJECT ENGINEER:
FRANK SENTENO
DESCRIPTION | STATUS | COMMENTS |
|
REVISED | |
PRELIMINARY ENGINEERING | COMPLETED 04/14/09 | |
DESIGN & ENGINEERING (PS&E) | COMPLETED 07/27/09 | |
TO PW COMMISSION FOR REVIEW | N/A | |
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
CALTRANS ISSUED AUTHORIZATION TO PROCEED WITH CON- |
BID OPENING | COMPLETED 12/10/09 | STRUCTION 11/3/09 |
TO COUNCIL FOR AWARD | COMPLETED 01/12/10 | |
BEGIN CONSTRUCTION | COMPLETED 04/05/10 | |
END CONSTRUCTION | 07/23/10 | |
PROJECT NO. CIP 02-612 PUBLIC WORKS YARD RENOVATION – PHASE 2 – PROJECT ENGINEER: KEN REAMEY
DESCRIPTION | STATUS | COMMENTS |
| REVISED | |
PRELIMINARY ENGINEERING | COMPLETED 09/18/06 |
DESIGN & ENGINEERING (PS&E) | 01/11 | |
TO PW COMMISSION FOR REVIEW | N/A | |
ADVERTISE | TBD | |
BID OPENING | TBD | |
TO COUNCIL FOR AWARD | TBD | |
BEGIN CONSTRUCTION | TBD | |
END CONSTRUCTION | TBD | |
PROJECT NO. CIP 99-631 BEACH RESTROOMS AT 2ND, 14TH, & 22ND STREETS – REHABILITATION – PROJECT ENGINEER: KEN REAMEY
DESCRIPTION | STATUS | COMMENTS |
| REVISED | |
PRELIMINARY ENGINEERING | COMPLETED 03/11/08 | |
DESIGN & ENGINEERING (PS&E) | 08/12/10 |
COASTAL COMMISSION & ENVIRONMENTAL |
PLANNING COMMISSION APPROVAL | COMPLETED 06/16/09 | |
TO PW COMMISSION FOR REVIEW | COMPLETED 05/21/08 | |
COASTAL COMMISSION APPROVAL | 06/11/10 |
|
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
|
BID OPENING | 12/16/10 | RE-BID PROJECT FOR TWO
RESROOMS ONLY |
TO COUNCIL FOR AWARD | 01/11 | |
BEGIN CONSTRUCTION | 02/11 | |
END CONSTRUCTION | 06/11 | |
PROJECT NO. CIP 09-659 PARKING STRUCTURE & PIER REPAIRS – PROJECT ENGINEER: KEN REAMEY
DESCRIPTION | STATUS | COMMENTS |
| | |
PRELIMINARY ENGINEERING | COMPLETED 01/27/10 |
PIER ASSESSMENT RECEIVED |
DESIGN & ENGINEERING (PS&E) | 04/15/10 | PIER
REPAIRS |
TO PW COMMISSION FOR REVIEW | N/A | |
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A | |
BID OPENING | COMPLETED 05/11/10 | PIER REPAIRS |
TO COUNCIL FOR AWARD | COMPLETED 06/08/10 | PIER REPAIRS |
BEGIN CONSTRUCTION | 07/19/10 | PIER REPAIRS |
END CONSTRUCTION | 07/26/10 | PIER REPAIRS |
* TBD - TO BE DETERMINED