Recommendation:
It is recommended that Council receive and file this report.
Summary:
This report gives the status of capital improvement projects that are either under design or construction. Capital improvement projects not indicated in this report can be found in the department's Monthly Activity Report.
Project Status:
PROJECT NO. CIP 08-127 STREET IMPROVEMENTS, PROJECT ENGINEER: FRANK SENTENO
DESCRIPTION | STATUS | COMMENTS |
| REVISED | |
PRELIMINARY ENGINEERING | COMPLETED 09/18/08 | |
DESIGN & ENGINEERING (PS&E) | COMPLETED 01/20/11 | |
TO PW COMMISSION FOR REVIEW | N/A | |
TO COUNCIL FOR APPROVAL TO ADVERTISE | COMPLETED 01/11/11 | |
BID OPENING | COMPLETED 02/17/11 | |
TO COUNCIL FOR AWARD | COMPLETED 04/26/11 | |
BEGIN CONSTRUCTION | 06/11 | |
END CONSTRUCTION | 08/11 | |
PROJECT NO. CIP 02-612 PUBLIC WORKS YARD RENOVATION – PHASE 2 – PROJECT ENGINEER: KEN REAMEY
DESCRIPTION | STATUS | COMMENTS |
| REVISED | |
PRELIMINARY ENGINEERING | COMPLETED 09/18/08 | |
DESIGN & ENGINEERING (PS&E) | 08/11 | |
TO PW COMMISSION FOR REVIEW | N/A | |
TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD | |
BID OPENING | TBD | |
TO COUNCIL FOR AWARD | TBD | |
BEGIN CONSTRUCTION | TBD | |
END CONSTRUCTION | TBD | |
PROJECT NO. CIP 99-631 BEACH RESTROOMS AT 2ND, 14TH, & 22ND STREETS – REHABILITATION – PROJECT ENGINEER: KEN REAMEY
DESCRIPTION | STATUS | COMMENTS |
| REVISED | |
PRELIMINARY ENGINEERING | COMPLETED 03/11/08 | |
DESIGN & ENGINEERING (PS&E) | 08/12/10 |
COASTAL COMMISSION & ENVIRONMENTAL |
PLANNING COMMISSION APPROVAL | COMPLETED 06/16/09 | |
TO PW COMMISSION FOR REVIEW | COMPLETED 05/21/08 | |
COASTAL COMMISSION APPROVAL | 06/11/10 |
|
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
|
BID OPENING | 12/16/10 | RE-BID PROJECT FOR TWO
RESROOMS ONLY |
TO COUNCIL FOR AWARD | 3/22/11 | |
BEGIN CONSTRUCTION | 05/03/11 | |
END CONSTRUCTION | 09/11 | |
PROJECT NO. CIP 09-659 PARKING STRUCTURE & PIER REPAIRS – PROJECT ENGINEER: KEN REAMEY
DESCRIPTION | STATUS | COMMENTS |
| | |
PRELIMINARY ENGINEERING | COMPLETED 01/27/10 |
PIER ASSESSMENT RECEIVED |
DESIGN & ENGINEERING (PS&E) | 04/15/10 | PIER
REPAIRS |
TO PW COMMISSION FOR REVIEW | N/A | |
TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A | |
BID OPENING | COMPLETED 05/11/10 | PIER REPAIRS |
TO COUNCIL FOR AWARD | COMPLETED 06/08/10 | PIER REPAIRS |
BEGIN CONSTRUCTION | 07/19/10 | PIER REPAIRS |
END CONSTRUCTION | 07/26/10 | PIER REPAIRS |
PROJECT NO. CIP 10-426 SEWER IMPROVEMENTS PROJECT, CITYWIDE -PROJECT ENGINEER: FRANK SENTENO
DESCRIPTION | STATUS | COMMENTS |
| | |
PRELIMINARY ENGINEERING | COMPLETED 01/13/11 |
|
DESIGN & ENGINEERING (PS&E) | COMPLETED 04/11 | |
TO PW COMMISSION FOR REVIEW | COMPLETED 02/16/11 | |
TO COUNCIL FOR APPROVAL TO ADVERTISE | 06/11 | |
BID OPENING | 07/11 | |
TO COUNCIL FOR AWARD | 07/11 | |
BEGIN CONSTRUCTION | 08/11 | |
END CONSTRUCTION | | |
PROJECT NO. CIP TBD HERMOSA VALLEY SCHOOL, VALLEY DR./ARDMORE AVE. AT 16TH ST. & GREENBELT (HSIP)-PROJECT ENGINEER: H. BEHBOODI
DESCRIPTION | STATUS | COMMENTS |
| | |
PRELIMINARY ENGINEERING | COMPLETED 1/13/11 |
|
DESIGN & ENGINEERING (PS&E) | COMPLETED 04/11 | |
TO PW COMMISSION FOR REVIEW | COMPLETED 02/16/11 | |
TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD | |
BID OPENING | TBD | |
TO COUNCIL FOR AWARD | TBD | REQUIRES
CALTRANS AUTHORIZATION TO PROCEED |
BEGIN CONSTRUCTION | TBD | WITH
CONSTRUCTION |
END CONSTRUCTION | | |
* TBD - TO BE DETERMINED